Difference between revisions of "Jan 12, 2011 SiPM Electrical and Cooling"
From GlueXWiki
(→Minutes) |
|||
Line 27: | Line 27: | ||
# Schedule, reporting, and manpower (Elton) | # Schedule, reporting, and manpower (Elton) | ||
# SiPM production testing (everyone) | # SiPM production testing (everyone) | ||
+ | #* One electronics board is ready. Carl will pick it up and install. Chris will assemble the other three shortly | ||
+ | #* Chris has the cable to connect to bias power supply. Carl can also pick that one up | ||
+ | #* Testing of light uniformity is done, a calibration is still needed. | ||
+ | #* Yi is working with computer center to establish communication with PS. All other devices are connected. | ||
+ | #* Can start checking testing station next week. | ||
# Mechanical assembly (Scot) | # Mechanical assembly (Scot) | ||
# Mechanical (Jim) | # Mechanical (Jim) | ||
# Mechanical drawings (Chuck) | # Mechanical drawings (Chuck) | ||
# Temperature compensation (Jack) | # Temperature compensation (Jack) | ||
+ | #* Still needs to send values of trim resistors to Chris. | ||
# Preamp-summing (Fernando/Chris) | # Preamp-summing (Fernando/Chris) | ||
+ | #* Revised board with correct standoff holes is ready for checking by Fernando | ||
+ | #* Will send out to fab as soon as ready | ||
+ | #* Expect to have operational boards by third week in Feb. | ||
+ | # SiPM testing (Ivan) | ||
+ | #* Laser has been installed in the lab. Waiting on LSOP from Fernando to power up and use. | ||
+ | #* Should start timing measurements with laser next week. |
Revision as of 18:29, 12 January 2012
Action Items from previous meetings
-
U-boards need to be ordered for the mini-Bcal (Chris)10 boards ordered to check before ordering more -
Cables need to be ordered for the SiPM production test setup (Chris)Cables have been ordered - Values of trim resistors for nominal operation to Chris (Jack). Chris to add them to the BOM.
-
Order any missing mechanical parts for assembly of mini-Bcal (Jim)All parts are in hand. Cooling plates are being modified to ease attachment of cooling tube.
Tentative Agenda
- Announcements
- Action Items
- Schedule, reporting, and manpower (Elton)
- SiPM production testing (everyone)
- Mechanical assembly (Scot)
- Mechanical (Jim)
- Mechanical drawings (Chuck)
- Temperature compensation (Jack)
- Preamp-summing (Fernando/Chris)
- SiPM testing (Ivan)
Minutes
Attending: Chris, Ivan, Elton, Jim, Yi, Carl, Eugene
- Announcements
- Action Items
- Schedule, reporting, and manpower (Elton)
- SiPM production testing (everyone)
- One electronics board is ready. Carl will pick it up and install. Chris will assemble the other three shortly
- Chris has the cable to connect to bias power supply. Carl can also pick that one up
- Testing of light uniformity is done, a calibration is still needed.
- Yi is working with computer center to establish communication with PS. All other devices are connected.
- Can start checking testing station next week.
- Mechanical assembly (Scot)
- Mechanical (Jim)
- Mechanical drawings (Chuck)
- Temperature compensation (Jack)
- Still needs to send values of trim resistors to Chris.
- Preamp-summing (Fernando/Chris)
- Revised board with correct standoff holes is ready for checking by Fernando
- Will send out to fab as soon as ready
- Expect to have operational boards by third week in Feb.
- SiPM testing (Ivan)
- Laser has been installed in the lab. Waiting on LSOP from Fernando to power up and use.
- Should start timing measurements with laser next week.