= Action Item List = (updated - see bottom of page)
+
= Tentative Agenda =
 +
 
 +
# Announcements
 +
# Swager reactivation
 +
# Beam/plate leveling on machining and layup tables
 +
# Installation: how to lift matrix from Al base plate off steel beam
 +
# Latest changes to drawings
 +
# Review action item list
 +
# Other business
 +
 
 +
= Action Item List =
  
 
# <strike>Tim will supply updated drawings and post on DocDB by this friday</strike>
 
# <strike>Tim will supply updated drawings and post on DocDB by this friday</strike>
Line 31: Line 41:
 
#* Construction Manager: Progress at UofA on job description, job ad
 
#* Construction Manager: Progress at UofA on job description, job ad
 
#* Co-Op job ads
 
#* Co-Op job ads
 
= Tentative Agenda =
 
 
# Announcements
 
# Swager reactivation
 
# Beam/plate leveling on machining and layup tables
 
# Installation: how to lift matrix from Al base plate off steel beam
 
# Latest changes to drawings
 
# Review action item list
 
# Other business
 
  
 
= Minutes =
 
= Minutes =
  
 
''Attendees: Regina - Zisis, George, Dan, Keith  Alberta - Gilbert, Jan, JLAB - Tim, James''
 
''Attendees: Regina - Zisis, George, Dan, Keith  Alberta - Gilbert, Jan, JLAB - Tim, James''

Revision as of 12:42, 19 January 2009

Teleconference Instructions

Meeting time 14:00-15:00 Newport News / 13:00-14:00 Regina / 12:00-13:00 Edmonton

  • +1-800-377-8846 : US
  • +1-888-276-7715 : Canada
  • +1-302-709-8424 : International
  • then enter participant code: 39527048# (remember the "#")

Quick Reference Links

Documents to Review

  1. Updated Wedge drawing: Latest wedge machined dwg
  2. Updated Base plate drawing: Latest base plate dwg need to remove inserts for machining

Tentative Agenda

  1. Announcements
  2. Swager reactivation
  3. Beam/plate leveling on machining and layup tables
  4. Installation: how to lift matrix from Al base plate off steel beam
  5. Latest changes to drawings
  6. Review action item list
  7. Other business

Action Item List

  1. Tim will supply updated drawings and post on DocDB by this friday
  2. Swager reactivation and rolling spacing check (Zisis/George)
  3. Gilbert will submit a list of all tools required and cost estimates by middle of next week. Mostly completed.
  4. Gilbert will send a drawing of the machining set up for Jlab to reference.
  5. Detailed schedule for preparation for module production (Gilbert).
  6. Tim to supply 3d stp/iges files to Regina/Alberta.
  7. In progress: George submitted a QA plan last month. Needs to be reviewed by Tim and Elke.
  8. Manpower
    • Construction Manager: Progress at UofA on job description, job ad
    • Co-Op job ads

Minutes

Attendees: Regina - Zisis, George, Dan, Keith Alberta - Gilbert, Jan, JLAB - Tim, James