(Created page with "== Meeting Time and Place == Thursday January 13, 2022, 3:00pm Bluejeans https://bluejeans.com/465620466 * Present - Elton, Dave, Stephanie, Ilya, Rory, Mark S, Beni, Simon,...")
 
Line 15: Line 15:
 
** Steel absorbers have been fiducialized
 
** Steel absorbers have been fiducialized
 
* Installation/assy 3D Model and dwgs all completed except Microscope move
 
* Installation/assy 3D Model and dwgs all completed except Microscope move
** LV attach
+
** LV attach and ground
** Scintillator orientation
+
** Chamber order
 
* Microscope move
 
* Microscope move
 
* Target Design in work [[image:cpp_target5.jpg|thumb]] [[image:cpp_target6.jpg|thumb]] [[image:cpp_target7.jpg|thumb]] [[image:cpp_target8.jpg|thumb]]
 
* Target Design in work [[image:cpp_target5.jpg|thumb]] [[image:cpp_target6.jpg|thumb]] [[image:cpp_target7.jpg|thumb]] [[image:cpp_target8.jpg|thumb]]

Revision as of 17:01, 12 January 2022

Meeting Time and Place

Thursday January 13, 2022, 3:00pm Bluejeans https://bluejeans.com/465620466

  • Present - Elton, Dave, Stephanie, Ilya, Rory, Mark S, Beni, Simon, Mark I, Anthony

Agenda

Cpp install chambers.pdf Cpp S&A chambers.pdf 
    • Steel absorbers have been fiducialized
  • Installation/assy 3D Model and dwgs all completed except Microscope move
    • LV attach and ground
    • Chamber order
  • Microscope move
  • Target Design in work
    Cpp target5.jpg
    Cpp target6.jpg
    Cpp target7.jpg
    Cpp target8.jpg
    • Most parts made (a good portion are 3D printed)
    • Will do a test assy next week


  • Things to work out
    • Gas system, manifold/bubblers (Beni has some)
    • Complete structural analysis - approved by Tom Renzo - need to release into system
    • Develop Detailed installation plan
    • Develop Design/operational/Maintenance Requirements
    • Modified US vacuum system
    • Solid target installation
    • Installation drawing including Microscope move
    • CPP Detector operations in Hall D OSP
    • Possible use of nitrogen flow for cooling electronics in Faraday cage

Minutes

Action Items