== Minutes and Action Items ==
 
== Minutes and Action Items ==
* Request for ERR submitted
 
* We need to show that everything is in place for a successful experiment
 
** Design status
 
** Procurement schedule/status
 
** Installation schedule
 
*** For installing prior to 2022 run - full detector then uninstall a portion to run Primex
 
*** For Installing in middle of 2022 run
 
** Installation procedure
 
** Manpower availability
 
** Calibration and Analysis procedures
 
** Need Safety documents
 
** OSP
 
** Installation procedure/HDlist
 
** EESAD
 
** COO
 
 
* Will use CDC Gas system and crates
 
* Signal cables needed
 
* Elton to write OSP
 
* Elton to start ERR web page (use DIRC as an example)
 
* Tim to update install schedule to show 2 scenarios
 
* Tim to Start installation plan
 
* Rory to get wire chambers working
 
* Tim and Stephanie to complete support stand drawing package
 

Revision as of 17:18, 13 January 2021

Meeting Time and Place

Thursday Jan 14, 2021, 2pm Bluejeans https://bluejeans.com/465620466

  • Present - Elton, Dave, Stephanie, Ilya, Rory, Mark S

Agenda

          Media:CPP_Schedule_before_primex.pdf 
          Media:CPP_Schedule_after_primex.pdf
  • Solid Pb target support and installation Media:CPP_Target_pic.pdf
  • Beam vacuum pipe needed for the experiment. (Target is located at z=1 cm, 64 cm upstream of nominal GlueX)
  • Relocation of CDC FADC electronics for use with the muon chamber Media:CPP_Electronics_enclosure.pdf
  • Review that there are no interferences for the new grounding shields for the muon chamber electronics.
  • Design/Procurement status
  • Things to work out
    • Gas line manifold
    • Complete structural analysis
    • Develop Detailed installation plan
    • Develop Design/operational/Maintenance Requirements
    • Modified US vacuum system
    • Solid target installation

Minutes and Action Items