Difference between revisions of "January 14, 2021 CPP Design Meeting ERR discussion"

From GlueXWiki
Jump to: navigation, search
(Agenda)
(Minutes and Action Items)
 
(5 intermediate revisions by 2 users not shown)
Line 7: Line 7:
 
== Agenda ==
 
== Agenda ==
 
* Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/December_17,_2020_CPP_Design_Meeting
 
* Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/December_17,_2020_CPP_Design_Meeting
* Readiness Review Mid February? [[Media:HallD_CPP-NPP_charge.pdf]]
+
* Readiness Review February 10
 +
** Charge [[Media:HallD_CPP-NPP_charge.pdf]]
 +
** Agenda?
 +
** [[CPP and NPP Readiness Review]]
 
* Schedule  
 
* Schedule  
           [[Media:CPP_Schedule_before_primex.pdf]]  
+
           [[Media:CPP_Schedule_before_primex_v2.pdf]]  
 
           [[Media:CPP_Schedule_after_primex.pdf]]
 
           [[Media:CPP_Schedule_after_primex.pdf]]
 
* Solid Pb target support and installation [[Media:CPP_Target_pic.pdf]]  
 
* Solid Pb target support and installation [[Media:CPP_Target_pic.pdf]]  
Line 25: Line 28:
  
 
== Minutes and Action Items ==
 
== Minutes and Action Items ==
 +
* ERR discussed - 3 talks to address charge questions
 +
** Decided to use schedule with CPP run first then Primex - keep other as backup
 +
* Target Discussion
 +
** Rory has target from previous experiment we will use (lead)
 +
** Need manual insertion of lead and empty target with good precision (change 1X per day)
 +
** Need vacuum right up to target (thin kapton window -125 microns)
 +
** Desire helium bag inside CDC
 +
** Need to develop design for target change out that can be done quickly and precisely
 +
** Target location 64 cm US of existing target (Hall D 1 cm US of 0,0)
 +
** Vacuum system needs to be designed -continue 1.5 inch tube
 +
* Need to develop talks for CPP review to address charge
 +
* Detector move DS 3 inches to make room in Darkroom for library ladder

Latest revision as of 12:46, 28 January 2021

Meeting Time and Place

Thursday Jan 14, 2021, 2pm Bluejeans https://bluejeans.com/465620466

  • Present - Elton, Dave, Stephanie, Ilya, Rory, Mark S

Agenda

          Media:CPP_Schedule_before_primex_v2.pdf 
          Media:CPP_Schedule_after_primex.pdf
  • Solid Pb target support and installation Media:CPP_Target_pic.pdf
  • Design/Procurement status
  • New Detector position - 3 inches DS to make dark room bigger
  • Things to work out
    • Gas line manifold
    • Complete structural analysis
    • Develop Detailed installation plan
    • Develop Design/operational/Maintenance Requirements
    • Modified US vacuum system
    • Solid target installation
    • Documentation for ERR

Minutes and Action Items

  • ERR discussed - 3 talks to address charge questions
    • Decided to use schedule with CPP run first then Primex - keep other as backup
  • Target Discussion
    • Rory has target from previous experiment we will use (lead)
    • Need manual insertion of lead and empty target with good precision (change 1X per day)
    • Need vacuum right up to target (thin kapton window -125 microns)
    • Desire helium bag inside CDC
    • Need to develop design for target change out that can be done quickly and precisely
    • Target location 64 cm US of existing target (Hall D 1 cm US of 0,0)
    • Vacuum system needs to be designed -continue 1.5 inch tube
  • Need to develop talks for CPP review to address charge
  • Detector move DS 3 inches to make room in Darkroom for library ladder