Line 13: Line 13:
 
* Solid Pb target support and installation [[Media:CPP_Target_pic.pdf]]  
 
* Solid Pb target support and installation [[Media:CPP_Target_pic.pdf]]  
 
* Design/Procurement status
 
* Design/Procurement status
 +
* New Detector position - 3 inches DS to make dark room bigger
  
 
* Things to work out
 
* Things to work out

Revision as of 17:22, 13 January 2021

Meeting Time and Place

Thursday Jan 14, 2021, 2pm Bluejeans https://bluejeans.com/465620466

  • Present - Elton, Dave, Stephanie, Ilya, Rory, Mark S

Agenda

          Media:CPP_Schedule_before_primex.pdf 
          Media:CPP_Schedule_after_primex.pdf
  • Solid Pb target support and installation Media:CPP_Target_pic.pdf
  • Design/Procurement status
  • New Detector position - 3 inches DS to make dark room bigger
  • Things to work out
    • Gas line manifold
    • Complete structural analysis
    • Develop Detailed installation plan
    • Develop Design/operational/Maintenance Requirements
    • Modified US vacuum system
    • Solid target installation
    • Documentation for ERR