January 18, 2024 KLONG KPT post Review Design Meeting

From GlueXWiki
Revision as of 15:59, 18 January 2024 by Whitey (Talk | contribs) (Created page with "== Meeting Time and Place == Thursday January 18, 2024, 1pm Zoom https://jlab-org.zoomgov.com/j/1611857466?pwd=VEZndTZzdDdNOUdJU3NxblRLcVoxdz09&from=addon * Invited - Hova...")

(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to: navigation, search

Meeting Time and Place

Thursday January 18, 2024, 1pm

Zoom https://jlab-org.zoomgov.com/j/1611857466?pwd=VEZndTZzdDdNOUdJU3NxblRLcVoxdz09&from=addon

  • Invited - Hovanes Egiyan, Stephanie Worthington, Keith Harding, Igor Strakovsky, Tim Whitlatch, Vitaly Baturin,
Eugene Chudakov, Josh Ballard

Agenda

Discuss changes being made as a result of the review last fall


Minutes/Actions

  • Tungsten absorber changed from 15.2 cm square to 14.2 cm square
  • Is existing 10" Kapton window adequate for KLONG radiation dosage? (Igor/Tim)
  • Is there enough space for a profiler and active collimator?
    • Assume current AC and new profiler
    • Bring AC and profiler 3D models into existing KPT model (Keith)
  • Need to flip the location of the KPT assy to move north upon reinstall of GlueX (Keith)
  • Need to address thermal fatigue of tungsten and beryllium by June (Tim)
  • The review recommended an FMEA be performed for system failures such as cooling and power (Tim)
  • Need to develop a plan for decommissioning and design but not procure the needed items (Tim)
  • Make sure the tungsten composition is defined properly in power deposition and thermal models (Tim/Vitaly
  • Hall A had some experience with tungsten heating
  • We need to make sure RADCON approves the current design (Hovanes)
  • Need to reissue overall layout for review (Keith)

Action Items