Difference between revisions of "January 21, 2022 Tech group SAD meeting"
From GlueXWiki
(→Agenda) |
(→Agenda) |
||
(5 intermediate revisions by the same user not shown) | |||
Line 7: | Line 7: | ||
== Agenda == | == Agenda == | ||
* Safety - CPP Stand install | * Safety - CPP Stand install | ||
− | * Hall D SAD Tasks | + | * Hall D SAD Tasks [[Media:SAD2022_Acc_schedule.pdf]] |
** CPP INstall O:\halld_engineering\Installation Schedules | ** CPP INstall O:\halld_engineering\Installation Schedules | ||
*** Microscope move - Mostly completed - will need to re-install Hodoscope once tested | *** Microscope move - Mostly completed - will need to re-install Hodoscope once tested | ||
Line 24: | Line 24: | ||
** Target Turbo repair | ** Target Turbo repair | ||
** TEDF move in late March-early April | ** TEDF move in late March-early April | ||
+ | ** New electric quads for PS parasitic detectors installed | ||
* JT file creation | * JT file creation | ||
* FCAL Insert Drawings | * FCAL Insert Drawings | ||
Line 33: | Line 34: | ||
* NMR controller repair | * NMR controller repair | ||
− | * Set up PS | + | * Set up PS parasitic meeting |
* Decide on Goni maintenance | * Decide on Goni maintenance | ||
+ | * Delineate ePAS permit requests for CPP install HDList |
Latest revision as of 15:01, 21 January 2022
Meeting Time and Place =
Thursday January 21, 2022 at 8:00 am Hall D Counting House
Zoom https://jlab-org.zoomgov.com/j/1601557064?pwd=NkF5d1BOdm1INHE4Vkw0NXpMT00rZz09&from=addon#success
Agenda
- Safety - CPP Stand install
- Hall D SAD Tasks Media:SAD2022_Acc_schedule.pdf
- CPP INstall O:\halld_engineering\Installation Schedules
- Microscope move - Mostly completed - will need to re-install Hodoscope once tested
- Platform mods - completed
- Lead absorber
- Move Chambers to Hall for Beni/Elton to check HV on wires
- Bring stand to hall
- Solenoid Warm Up/Cool Down - 62K - lots of nitrogen liquid level alarms
- Goniometer Maintenance/Diamonds?
- PS Parasitic Detectors stages?
- DIRC Resurrection - Justin to come in Tuesday to look at test pieces
- FCAL Insert Module fabrication ?
- Tagger NMR repair - RMA available
- FDC chiller repair
- BCAL Coldshot Chiller commissioning
- Target Turbo repair
- TEDF move in late March-early April
- New electric quads for PS parasitic detectors installed
- CPP INstall O:\halld_engineering\Installation Schedules
- JT file creation
- FCAL Insert Drawings
- General Maintenance
- On Call - Bobby
- ePAS Training and trial https://www.jlab.org/esh/epas
Action Items
- NMR controller repair
- Set up PS parasitic meeting
- Decide on Goni maintenance
- Delineate ePAS permit requests for CPP install HDList