* We discussed the beampipe downstream of the beryllium target. Currently there is a 3.5 cm opening in the pipe going into the Pair Spectrometer magnet. Since the beam spot size on the beryllium is about 4 cm, the PS vacuum chamber would need to be replaced with a 6cm opening beam pipe and be at least 6 cm downstream of this.
  
 
== Action Items ==
 
== Action Items ==

Revision as of 16:08, 21 July 2021

Meeting Time and Place

Thursday July 08, 2021, 1pm Bluejeans https://bluejeans.com/465620466

  • Present - Hovanes Egiyan, Moskov Amaryan, Stephanie Worthington, Keith Harding, Igor Strakovsky, Tim Whitlatch, Mark Stevens

Agenda

  • Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/June_24,_2021_KLONG_Design_Meeting
  • Media:KLONG_Be_target_overall.pdf
  • Existing PS vacuum chamber 5 cm high, entrance tube 3.5 cm round ID, magnet gap - 7 cm
  • Tungsten cooling
  • Preliminary 3D Model
    • Support/rollers
    • Tungsten cooling
    • 7 cm tube downstream to allow cooling tubes for tungsten
    • Be target holder
    • lead geometry
    • Borated Poly geometry
  • Heat absorbed by Be and Tungsten (.6kw and 6Kw respectively)
  • Requirements:
    • Cool tungsten plug to below temperature that affects lead (327°C)
    • 6 cm beam tube near final target
    • Moveable out of beamline
    • Be 98% pure or better

Minutes and Action Items

  • We discussed the beampipe downstream of the beryllium target. Currently there is a 3.5 cm opening in the pipe going into the Pair Spectrometer magnet. Since the beam spot size on the beryllium is about 4 cm, the PS vacuum chamber would need to be replaced with a 6cm opening beam pipe and be at least 6 cm downstream of this.

Action Items