Difference between revisions of "June 11, 2009 Calorimetry"
From GlueXWiki
(→Items for followup from previous meeting(s)) |
(→Tentative Agenda) |
||
Line 27: | Line 27: | ||
# Simulations | # Simulations | ||
# BCAL Fabrication | # BCAL Fabrication | ||
− | #* Contract | + | #* Contract status |
− | #* | + | #* Construction prototype update |
#* Report on First-article fibers (Zisis) | #* Report on First-article fibers (Zisis) | ||
− | |||
− | |||
# BCAL Readout | # BCAL Readout | ||
− | #* | + | #* Update from USM (Will) |
− | + | #* Rates in the BCAL (Sasha) | |
− | #* Rates in the BCAL | + | #* Budget comparisons (Elton) |
− | #* | + | #* Review of readout options (tentative July 21) discussion |
− | #* Review of readout options (tentative July | + | |
=Minutes= | =Minutes= |
Revision as of 08:55, 10 June 2009
Teleconference Time: 11:00 a.m. EST
- EVO session
- Phone:
- +1-800-377-8846 : US
- +1-888-276-7715 : Canada
- +1-302-709-8424 : International
- then enter participant code: 39527048# (remember the "#")
Contents
Items for followup from previous meeting(s)
- Resolution studies
- Develop criteria for evaluating resolution studies
- Study impact of inactive material at the end of BCAL on acceptance.
- Documentation on fiber first-article
- Review calibration procedures
- Will: Noted from CLAS experience both oxides and carbonates can accumulate on lead. One type is worse than the other (will send references to UofR)
-
Elton will check on fiber delivery and comments from Kuraray on material for storage of fibers.
Documents to Review
Tentative Agenda
- Announcements
- Review of Action Items
- Calibration
- FCAL Update
- Simulations
- BCAL Fabrication
- Contract status
- Construction prototype update
- Report on First-article fibers (Zisis)
- BCAL Readout
- Update from USM (Will)
- Rates in the BCAL (Sasha)
- Budget comparisons (Elton)
- Review of readout options (tentative July 21) discussion