June 18, 2020 CPP Design Meeting

From GlueXWiki
Revision as of 08:29, 10 July 2020 by Whitey (Talk | contribs) (Minutes and Action Items)

(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to: navigation, search

Meeting Time and Place =

Thursday June 18, 2020, 1:30pm Bluejeans https://bluejeans.com/735541157/3638?src=calendarLink

  • Present - Elton, Dave, Stephanie, Ilya, Rory (remote)

Agenda

Assume that nominal the GlueX configuration consists of

  • No Pb shielding
  • DIRC installed
  • Solenoid field at 1350 A

CPP Test Configuration

  • With and without Pb shielding
  • DIRC removed
  • Solenoid field at 1350 A (no change)
    • CPP test DAQ setup: 2 hrs
    • Repeat measurement with nominal GlueX configuration: 2 hrs
    • Configure experiment for CPP Test: 38 hours
    • Start with no DIRC, no shielding
    • Take data: 2 hours
    • Install Pb shielding: 6 hours
    • Take data: 2 hours
    • Restore nominal GlueX configuration: 26 hours.

Total time = 2 + 2 + 38 + 2 + 6 + 2 + 26 = 76 hours ~ 3 days

  • Things to work out
    • Gas line manifold
    • Adjustable lead absorber
    • Alignment hardware
    • Complete structural analysis
    • Develop Detailed installation plan
    • Develop Design/operational/Maintenance Requirements

Minutes and Action Items

  • Reviewed minutes of last meeting
  • Ilya presented simulation and showed 1/2 steel bolts through the adjustable lead is fine
  • work on details of beam tests this summer (Bobby)
    • Lead should be as close to TOF as possible
    • TOF in normal operating position
    • Work out install process/schedule with tech group
    • Ensure 18cm square opening in lead
  • Proceed with procurements as outlined
  • Set up new meeting in 2 weeks