Difference between revisions of "June 22, 2012 Fab Meeting"
From GlueXWiki
(→Agenda) |
(→Agenda) |
||
(2 intermediate revisions by the same user not shown) | |||
Line 5: | Line 5: | ||
== Agenda == | == Agenda == | ||
− | * ESH&Q minute - Heat protection Heat_Stress_Protectection_OSHA_NIOSH.pdf | + | * ESH&Q minute - Heat protection [[Media:Heat_Stress_Protectection_OSHA_NIOSH.pdf]] |
* Announcements - ? | * Announcements - ? | ||
* FDC construction update - | * FDC construction update - | ||
Line 18: | Line 18: | ||
* Upcoming - this Summer to a Hall near you | * Upcoming - this Summer to a Hall near you | ||
** Cladding - next week? | ** Cladding - next week? | ||
+ | ** Painting | ||
** downstream carriage - July | ** downstream carriage - July | ||
** BCAL Production light guides - July | ** BCAL Production light guides - July | ||
Line 23: | Line 24: | ||
** Cryo Platform - End of August | ** Cryo Platform - End of August | ||
** Cryo group work | ** Cryo group work | ||
+ | * Tagger Installation |
Latest revision as of 12:37, 22 June 2012
Meeting Time and Place
Friday June 22, 2012 at 2:30pm At Jefferson Lab, the meeting will be held in room ARC 231
Agenda
- ESH&Q minute - Heat protection Media:Heat_Stress_Protectection_OSHA_NIOSH.pdf
- Announcements - ?
- FDC construction update -
- PS magnet vacuum chambers in - need to inspect
- Collimator beamline
- Solenoid controls/Power supply
- Tagger LCW
- Tagger stands
- Tagger/pair spec thin window test
- Counting House
- Electrical bonding
- Upcoming - this Summer to a Hall near you
- Cladding - next week?
- Painting
- downstream carriage - July
- BCAL Production light guides - July
- FCAL assembly - August
- Cryo Platform - End of August
- Cryo group work
- Tagger Installation