== Path Forward ==
 
== Path Forward ==
  
# Complete the 140A procedure including the quench balance and turn to turn short check not completed in the 15A test (to be completed and signed off by June 24)Complete
+
# Complete the 140A procedure including the quench balance and turn to turn short check not completed in the 15A test (to be completed and signed off by June 24) Complete
 
# Continue repair of refrigerator (to be completed by June 25)
 
# Continue repair of refrigerator (to be completed by June 25)
 
# Update preliminary analysis of quench and rationale for dump resistor and max current (June 25)
 
# Update preliminary analysis of quench and rationale for dump resistor and max current (June 25)

Revision as of 07:32, 25 June 2013

Thursday June 6,2013 at 11am At Jefferson Lab, the meeting will be held in room CC F326

Attendees

C. Rode, T. Whitlatch, E. Wolin, B. Flora (via phone for short duration..sorry), E. Chudakov, J. Creel, G. Young, P. Ghoshal

Agenda

  1. Release 140A procedure (Rev C) - George Media:140A Rev C.pdf complete
  2. Update hardware QD with new 10 turn pot and PLC with inductance algorithm - Elliot
  3. Clean up refrigerator and get ready for cooldown - Jonathan
  4. Finalize write up of quench analysis, dump resistor and max current rationale - George
  5. Continue low current ramp tests to categorize voltage spikes - Giles
  6. Write up high current portion of procedure (Rev D) - George Media:High Current Rev D.pdf
  7. Balance Power supply for 25H (if necessary based on 140A tests)- Giles
  8. Calculate what current we can safely run at at 5K 0.9K margin. Media:5K Quench Margins.pdf
  9. Set up meeting with Patrizia Tuesday for cooldown decision.
  • Are we ready to start cooldown?

Useful Info

  • Documents available at M:\halld_engineering\Solenoid\Commissioning\Response to Quench

Meeting Minutes

New Action Items

Path Forward

  1. Complete the 140A procedure including the quench balance and turn to turn short check not completed in the 15A test (to be completed and signed off by June 24) Complete
  2. Continue repair of refrigerator (to be completed by June 25)
  3. Update preliminary analysis of quench and rationale for dump resistor and max current (June 25)
  4. Initial review of updated write up by Bill Schneider and Bob Flora (June 26)
  5. Start refridge cooldown (to be started June 26th if agreed upon)
  6. Complete and sign off maximum current plan and quench analysis(to be completed by June 29)
  7. Start cooling magnet - July 8
  8. Perform 140A testing ( to be completed by July 21)
  9. Perform High current commissioning ( to be completed by July 23)
  10. Map magnet (to be completed by July 28)