Thursday June 6,2013 at 11am  
+
Thursday June 25,2013 at 11am  
At Jefferson Lab, the meeting will be held in room CC F326
+
At Jefferson Lab, the meeting will be held in room TED 2504
  
 
== Attendees ==
 
== Attendees ==
C. Rode, T. Whitlatch, E. Wolin, B. Flora (via phone for short duration..sorry), E. Chudakov, J. Creel, G. Young, P. Ghoshal
+
C. Rode, T. Whitlatch, E. Wolin, B. Flora (via Skype), E. Chudakov, J. Creel, G. Young, P. Ghoshal, George Biallas, Bill Schneider, Javier Gomez
  
 
== Agenda ==
 
== Agenda ==
* Discuss last weeks minutes https://halldweb1.jlab.org/wiki/index.php/June_20,_2013_Solenoid_Meeting
+
* Discuss last weeks minutes https://halldweb.jlab.org/wiki/index.php/June_20,_2013_Solenoid_Meeting
 
* Status of Action Items
 
* Status of Action Items
 
# Release 140A procedure (Rev C) - George  [[Media:140A Rev C.pdf]] complete
 
# Release 140A procedure (Rev C) - George  [[Media:140A Rev C.pdf]] complete
# Update hardware QD with new 10 turn pot and PLC with inductance algorithm - Elliot  
+
# Update hardware QD with new 10 turn pot and PLC with inductance algorithm - Elliot In work
# Clean up refrigerator and get ready for cooldown - Jonathan
+
# Clean up refrigerator and get ready for cooldown - Jonathan - In work
# Finalize write up of quench analysis, dump resistor and max current rationale  - George  
+
# Finalize write up of quench analysis, dump resistor and max current rationale  - George In work
# Continue low current ramp tests to categorize voltage spikes  - Giles
+
# Continue low current ramp tests to categorize voltage spikes  - Giles - In work
# Write up high current portion of procedure (Rev D) - George [[Media:High Current Rev D.pdf]]
+
# Write up high current portion of procedure (Rev D) - George [[Media:High Current Rev D.pdf]]1st cut out
# Balance Power supply for 25H (if necessary based on 140A tests)- Giles
+
# Balance Power supply for 25H (if necessary based on 140A tests)- Giles In work- Parts received from Danfysik
# Calculate what current we can safely run at at 5K  0.9K margin. [[Media:5K Quench Margins.pdf]]
+
# Calculate what current we can safely run at at 5K  0.9K margin. [[Media:5K Quench Margins.pdf]] Complete
# Set up meeting with Patrizia Tuesday for cooldown decision.
+
# Set up meeting with Patrizia Tuesday for cooldown decision. Complete
 
* Are we ready to start cooldown?
 
* Are we ready to start cooldown?
  
Line 23: Line 23:
  
 
== Meeting Minutes ==
 
== Meeting Minutes ==
Briefly went over last week's meeting minutes and path forward.
+
Discussed minutes from last mtg.
There has been alot of email chatter on the quench detector configuration. Bob Flora is happy with the current plan on using the software QD as the primary and the hardware as the secondary possible at a higher trip value.
+
With the new power supply ramping procedure, we see no voltage spike on going from zero current.
The PXI changes supporting this are done and the PLC changes should be complete early next week.
+
 
George will reissue the 140A procedure by tomorrow morning. High current preliminary procedure and the updated quench write up by COB Monday.
+
The current is lagging behind what it should be during the programmed ramp up. May be due to resistance in magnet with PS set to inductive or the PS not balanced to 25H. Will do further testing without magnet hooked up. Possibly change algorithm.
We will change out the dial pots on the hardware QD with a 10 turn balance pot and a 3 3/4 turn gain pot early next week.
+
 
Jonathan's crew is still working on the refrigerator and anticipates he will be ready for cooldown by next Wednesday.
+
Bill Schneider raised question of 1360A with dewar is slightly below .9K margin. Do we wish to do it?
Need to make a decision by Tuesday as whether or not to start cooldown of the refrigerator on Wednesday since Patrizia will be away from the lab starting Wednesday.
+
 
Discussion of turn to turn shorts determined that it is not worth the effort to do an R&D run to determine what can be detected.
+
Discussed the timing of the cooldown and testing - see "Path Forward" section below. Jonathan working on plan to allow liquid levels to drop to allow more time for superconducting testing.
It was suggested that we use a lower ramp rate at high currents to reduce any effects and George will incorporate this into the high current run procedure.
+
 
George and crew will continue with ramp rate test at low current to look at the effects on voltage spikes.
+
The minimum current for commissioning should be 1200A (by Aug 9)- do we do a full mapping at this current?
It was a general consensus that if the voltage spikes are small enough, the 25 Henry tuning hardware will not be installed until after mapping.
+
 
The current thinking for high current is to go to 1360A with dewar installed (from some lower current)and then go to 1350 and map the beamline location only. Then reduce to 1300A and fully map the magnet. When the dewar runs out it will not cause any pressure spikes.
+
Tuning PS to 25H - Decided to borrow a spare board from Hall C sister PS and test in our PS. If it works, modify the spare board according to Danfysik instructions. When it is ready, make decision on whether or not to implement.
We will assume the pressure spike from connecting the dewar will bring the temp to 5K (very conservative). Probir will determine the max current we can run at 5K with a .9K margin per Alcorn's spec.
+
 
It was also sgreed upon that it would be prudent to go to a slow dump if the PXI heartbeat dies.
+
Decision to change allowable voltage rise in the hardware QD to 500 mv. Also, the software QD integration time will be increased to 250msec for 100 mv limit.
 +
George will update rev. D of the procedure with high current running and these QD limit changes.
 +
 
 +
Probir calculated the max current at which we can add a Dewar to the system based on a 5K limit (with .9K margin). This would be 1200A
 +
 
 +
We discussed the pressure rise possibility during a fast dump. George will look at what happened at the 1260A fast dump from the heim column limit.
 +
Discussed adding a pressure relief solenoid valve for operations to keep the temp in the coils low if there is a refrigerator event. This will be looked at later for physics operations.
 +
 
 +
Decided to start field mapping the beam centerline location at 1000A - calibrate the hall probe using the NMR
 +
 
 +
Use 60hz filter for GFD as suggested by Bob Flora.
  
 
== New Action Items ==
 
== New Action Items ==
 +
 +
# Release High current procedure (Rev D)with discussed changes by July 1- George 
 +
# Update hardware QD with new 10 turn pot and PLC with inductance algorithm by July 1- Elliot
 +
# Clean up refrigerator and get ready for cooldown by July 3 - Jonathan - In work
 +
# Finalize write up of quench analysis, dump resistor and max current rationale  - George In work
 +
# Continue low current ramp tests to categorize voltage spikes/current lags  - Giles - In work
 +
# Check pressure rise during 1260A heim column fast dump - George
 +
# Get spare Inductance balancing board from Hall C and test in PS and modify if it works - Giles
 +
# Make decision on whether or not to install new PS balance hardware  - Eugene
 +
# Make decision on starting refrig cooldown be July 3rd - Jonathan
  
 
== Path Forward ==
 
== Path Forward ==
  
# Complete the 140A procedure including the quench balance and turn to turn short check not completed in the 15A test (to be completed and signed off by June 21)
+
# Complete and sign off maximum current plan and quench analysis(to be completed by July 1)
# Continue repair of refrigerator (to be completed by June 25)
+
# Continue cleanup of refrigerator (to be completed by July 3)
# Update preliminary analysis of quench and rationale for dump resistor and max current (June 25)
+
# Start refridge cooldown (Nitrogen cooldown be started July 6th if agreed upon)
# Initial review of updated write up by Bill Schneider and Bob Flora (June 26)
+
# Start Dewar transfers - July 8
# Start refridge cooldown (to be started June 27th if agreed upon)
+
# Start 140A testing - July 15
# Complete and sign off maximum current plan and quench analysis(to be completed by June 29)
+
# Start High current commissioning - July 22
# Start cooling magnet - July 8
+
# Map magnet July 23- 29
# Perform 140A testing ( to be completed by July 21)
+
# Perform High current commissioning ( to be completed by July 23)
+
# Map magnet (to be completed by July 28)
+

Latest revision as of 00:55, 1 April 2015

Thursday June 25,2013 at 11am At Jefferson Lab, the meeting will be held in room TED 2504

Attendees

C. Rode, T. Whitlatch, E. Wolin, B. Flora (via Skype), E. Chudakov, J. Creel, G. Young, P. Ghoshal, George Biallas, Bill Schneider, Javier Gomez

Agenda

  1. Release 140A procedure (Rev C) - George Media:140A Rev C.pdf complete
  2. Update hardware QD with new 10 turn pot and PLC with inductance algorithm - Elliot In work
  3. Clean up refrigerator and get ready for cooldown - Jonathan - In work
  4. Finalize write up of quench analysis, dump resistor and max current rationale - George In work
  5. Continue low current ramp tests to categorize voltage spikes - Giles - In work
  6. Write up high current portion of procedure (Rev D) - George Media:High Current Rev D.pdf1st cut out
  7. Balance Power supply for 25H (if necessary based on 140A tests)- Giles In work- Parts received from Danfysik
  8. Calculate what current we can safely run at at 5K 0.9K margin. Media:5K Quench Margins.pdf Complete
  9. Set up meeting with Patrizia Tuesday for cooldown decision. Complete
  • Are we ready to start cooldown?

Useful Info

  • Documents available at M:\halld_engineering\Solenoid\Commissioning\Response to Quench

Meeting Minutes

Discussed minutes from last mtg. With the new power supply ramping procedure, we see no voltage spike on going from zero current.

The current is lagging behind what it should be during the programmed ramp up. May be due to resistance in magnet with PS set to inductive or the PS not balanced to 25H. Will do further testing without magnet hooked up. Possibly change algorithm.

Bill Schneider raised question of 1360A with dewar is slightly below .9K margin. Do we wish to do it?

Discussed the timing of the cooldown and testing - see "Path Forward" section below. Jonathan working on plan to allow liquid levels to drop to allow more time for superconducting testing.

The minimum current for commissioning should be 1200A (by Aug 9)- do we do a full mapping at this current?

Tuning PS to 25H - Decided to borrow a spare board from Hall C sister PS and test in our PS. If it works, modify the spare board according to Danfysik instructions. When it is ready, make decision on whether or not to implement.

Decision to change allowable voltage rise in the hardware QD to 500 mv. Also, the software QD integration time will be increased to 250msec for 100 mv limit. George will update rev. D of the procedure with high current running and these QD limit changes.

Probir calculated the max current at which we can add a Dewar to the system based on a 5K limit (with .9K margin). This would be 1200A

We discussed the pressure rise possibility during a fast dump. George will look at what happened at the 1260A fast dump from the heim column limit. Discussed adding a pressure relief solenoid valve for operations to keep the temp in the coils low if there is a refrigerator event. This will be looked at later for physics operations.

Decided to start field mapping the beam centerline location at 1000A - calibrate the hall probe using the NMR

Use 60hz filter for GFD as suggested by Bob Flora.

New Action Items

  1. Release High current procedure (Rev D)with discussed changes by July 1- George
  2. Update hardware QD with new 10 turn pot and PLC with inductance algorithm by July 1- Elliot
  3. Clean up refrigerator and get ready for cooldown by July 3 - Jonathan - In work
  4. Finalize write up of quench analysis, dump resistor and max current rationale - George In work
  5. Continue low current ramp tests to categorize voltage spikes/current lags - Giles - In work
  6. Check pressure rise during 1260A heim column fast dump - George
  7. Get spare Inductance balancing board from Hall C and test in PS and modify if it works - Giles
  8. Make decision on whether or not to install new PS balance hardware - Eugene
  9. Make decision on starting refrig cooldown be July 3rd - Jonathan

Path Forward

  1. Complete and sign off maximum current plan and quench analysis(to be completed by July 1)
  2. Continue cleanup of refrigerator (to be completed by July 3)
  3. Start refridge cooldown (Nitrogen cooldown be started July 6th if agreed upon)
  4. Start Dewar transfers - July 8
  5. Start 140A testing - July 15
  6. Start High current commissioning - July 22
  7. Map magnet July 23- 29