Line 29: Line 29:
 
#*** Air flow considerations and plan
 
#*** Air flow considerations and plan
 
#* [[Media:DIRC_INSTALL_SCHEDULEv2.pdf|DIRC installation schedule]]
 
#* [[Media:DIRC_INSTALL_SCHEDULEv2.pdf|DIRC installation schedule]]
#* [[Media:DIRC_BBox_Flange_seal.pdf|DIRC BBox Split Flange Seal]]
+
#* [[Media:DIRC_BBox_Flange_seal.jpg|DIRC BBox Split Flange Seal]]
 
# Simulation studies (Maria and Roman)
 
# Simulation studies (Maria and Roman)
 
# MAPMT testing (Bill)
 
# MAPMT testing (Bill)
 
#* Magnetic field test
 
#* Magnetic field test
 
# AOB
 
# AOB

Revision as of 09:38, 27 June 2018

Meeting Information

GlueX DIRC Meeting
Thursday June 28, 2018
10:00 am, EDT
JLab room A110

Connection Using Bluejeans

  1. To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 846453895.
  2. To join via a Web Browser, go to the page [1] https://bluejeans.com/846453895 .
  3. To join via phone, use one of the following numbers and the Conference ID: 846453895
    • US or Canada: +1 408 740 7256 or
    • US or Canada: +1 888 240 2560
  4. More information on connecting to bluejeans is available.

Agenda

  1. Announcements
  2. Bar box transportation and installation: plans for a writeup? (Matt, et al.)
  3. Optical box
  4. Simulation studies (Maria and Roman)
  5. MAPMT testing (Bill)
    • Magnetic field test
  6. AOB