(Agenda)
(Agenda)
Line 6: Line 6:
 
* Work accomplished since last meeting
 
* Work accomplished since last meeting
 
** 15A test minus quench detector checks (magnet still resistive)
 
** 15A test minus quench detector checks (magnet still resistive)
 +
** Balanced GFD for 16ohm short
 
** Preliminary 140A test procedure written [[Media:140A procedure rev C.pdf]]
 
** Preliminary 140A test procedure written [[Media:140A procedure rev C.pdf]]
 
* Discuss path forward plan [[Media:wSchneider path forward.pdf]]
 
* Discuss path forward plan [[Media:wSchneider path forward.pdf]]
 
** Probirs margin comparison [[Media:Margin comparison.pdf]]
 
** Probirs margin comparison [[Media:Margin comparison.pdf]]
** George's info  [[Media:Quench plot zoom.png]]____ [[Media:Quench plot.png]]
+
* Refrigerator status
* Plans for low current testing
+
 
+
** Power Supply ramp smoothing program
+
** Power Supply resolution hardware fix (0-1.5 A/sec)
+
** Voltage tap checks/fixes
+
** Short to ground location
+
** Power Supply hose replacement
+
* Plans for low current testing
+
** 15A Commissioning Plan [[Media:15A Plan.pdf]]
+
** 140A Commissioning plan
+
* Cool Down Plans
+
 
* Path Forward .......
 
* Path Forward .......
  

Revision as of 13:36, 5 June 2013

Thursday June 6,2013 at 10am At Jefferson Lab, the meeting will be held in room ARC 231

Agenda

Useful Info

  • Documents available at M:\halld_engineering\Solenoid\Commissioning\Response to Quench

Meeting Minutes