MEDCON6 Shutdown Plan

From GlueXWiki
Revision as of 12:05, 22 March 2020 by Dalton (Talk | contribs) (Created page with "Based on the == ==T File:HCO_-_Hall_D_Mechanical_Hall_D_Shutdown_Checklist.pdf #* Cryo: keep magnets cold and full at 4k, set current to 0, park targets. Cryo in...")

(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to: navigation, search

Based on the

==

==T


File:HCO - Hall D Mechanical Hall D Shutdown Checklist.pdf


    • Cryo: keep magnets cold and full at 4k, set current to 0, park targets. Cryo in comms with Tim.


    • Magnet: Tim
      • Power down, secure cryo
    • Target: Chris Keith
      • Contact
    • Mechanical:
      • DIRC: Discussion with Justin and Tim. Would prefer to keep full and flowing. Keep
      • Mechanical on call (will it be possible?) Eugene: we must assume no maintenance. Ask Javier.
      • Detectors: Lubomir needs access.
      • Need gas. Cut flow in half, should have 5 weeks of gas. Bypass the alcohol bubbler.
      • BCAL: drain and flush with nitrogen
      • Training site managers on Hall D operations.
    • Electrical
      • Computers on
      • DAQ Crates OFF, control crates ON
      • Accelerator crates control PS, AC and vacuum. ON


Names for everything