MEDCON6 Shutdown Plan
From GlueXWiki
Revision as of 12:05, 22 March 2020 by Dalton (Talk | contribs) (Created page with "Based on the == ==T File:HCO_-_Hall_D_Mechanical_Hall_D_Shutdown_Checklist.pdf #* Cryo: keep magnets cold and full at 4k, set current to 0, park targets. Cryo in...")
Based on the
==
==T
File:HCO - Hall D Mechanical Hall D Shutdown Checklist.pdf
- Cryo: keep magnets cold and full at 4k, set current to 0, park targets. Cryo in comms with Tim.
- Magnet: Tim
- Power down, secure cryo
- Target: Chris Keith
- Contact
- Mechanical:
- DIRC: Discussion with Justin and Tim. Would prefer to keep full and flowing. Keep
- Mechanical on call (will it be possible?) Eugene: we must assume no maintenance. Ask Javier.
- Detectors: Lubomir needs access.
- Magnet: Tim
- Need gas. Cut flow in half, should have 5 weeks of gas. Bypass the alcohol bubbler.
- BCAL: drain and flush with nitrogen
- Training site managers on Hall D operations.
- Electrical
- Computers on
- DAQ Crates OFF, control crates ON
- Accelerator crates control PS, AC and vacuum. ON
- Electrical
Names for everything