Difference between revisions of "Mar 18, 2010 Calorimetry"
From GlueXWiki
(→Tentative Agenda) |
(→Items for followup from previous meeting(s)) |
||
Line 13: | Line 13: | ||
# Fcal | # Fcal | ||
#* Decision on rad hard detectors | #* Decision on rad hard detectors | ||
+ | #* Matt to coordinate with Christina on the shipment of glass blocks and pmts/dividers for monitoring system test. | ||
= Documents to Review= | = Documents to Review= |
Revision as of 14:51, 4 March 2010
Teleconference Time: 11:00 a.m. EST
- ESNET and EVO session
- Phone in CC F326 is 757-269-6337
- Phone in the Regina Videoconference Suite is 306-585-4204
- Phone only if requested:
- +1-800-377-8846 : US
- +1-888-276-7715 : Canada
- +1-302-709-8424 : International
- then enter participant code: 77438230# (remember the "#"). Phone line by request only.
Contents
Items for followup from previous meeting(s)
- Fcal
- Decision on rad hard detectors
- Matt to coordinate with Christina on the shipment of glass blocks and pmts/dividers for monitoring system test.
Documents to Review
Tentative Agenda
- Announcements
- Review of Action Items
- Calibration/Monitoring
- FCAL
- BCAL
- Other business
Minutes
Attendees:
- BCAL
- Construction
- All equipment operating nominally. Builds growing within tolerances.
- Mod 04 to RMS today or tomorrow; Mod 05 at 50%, Mod 06 at 10%. Two new crates arrived yesterday.
- Mod 02 and 03 machining most likely finished.
- Lead tally nearly done; some discrepancies. Will communicate with JLab and Vulcan today.
- Enough epoxy for 2.5 months on hand, 9 gallons back ordered.
- Shipping insurance sorted out and waiting to meet with shippers and get new quotations.
- Fibres
- Shipment 8 done and 100 fibres from No. 9 (see above links). Means shifted for shipment 9, for both Npe and atten length. Most likely a real effect but we're checking.
- RMS visit: March 5.
- Final contract will be given to RMS tomorrow.
- Inspection and pictures of Mod 02 and 03 machining.
- Transmission uniformity test on Module 01.
- Construction