Mar 19, 2020 Calorimeter

From GlueXWiki
Revision as of 13:14, 19 March 2020 by Elton (Talk | contribs) (Minutes)

Jump to: navigation, search

Meeting Time: 11:00 a.m.

  1. To join via a Web Browser, go to the page [1] https://bluejeans.com/907185247.
  2. To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 907185247.
  3. To join via phone, use one of the following numbers and the Conference ID: 907185247.
    • US or Canada: +1 408 740 7256 or
    • US or Canada: +1 888 240 2560
  4. Upon connection all microphones are automatically muted. To unmute your mike on a Polycom or equivalent unit, enter *4. Unmuting on a computer is trivial as there is a microphone button than can be clicked.
  5. More information on connecting to bluejeans is available.

Participant Direct Lines

  • JLab Phone in CC L207 is 757-269-7084 (usual room)
  • JLab Phone: in CC F326 is 757-269-6460
  • Phone in the Regina Video-conference Suite is 306-585-4204
  • Athens Phone: in Christina's office is 011-30-210-727-6947

References

  1. FCAL HDFCAL log book
  2. BCAL HDBCAL log book

Goals for Calorimetry Group

  1. Determine preliminary photon reconstruction efficiencies as a function of E, phi and theta in data and simulation with a point-to-point precision of at least 5%.
  2. Measure systematics of pi0/eta mass calibration as a function of detector position to a precision of at east 5 MeV.
  3. Demonstrate agreement of photon reconstruction efficiency and resolution between data and simulation as a function of E, phi and theta to within 5%.

Action Items

  1. Complete Calorimeter work packages

Long term items

Tentative Agenda

  1. Announcements
  2. Action Items
  3. Run Updates
    1. FCAL
    2. BCAL
  4. Calibrations
  5. Monitoring
  6. Reconstruction
  7. Efficiencies
  8. Simulations
  9. NIM articles
  10. Any other business

Minutes

Attending: Mark D., Elton, Jon, Tolga, Varun, Christina, Colin, Sean, Sasha, Karthik, Edmundo, Sean, Zisis, Churamani, Matt.

  1. Announcements
  2. First fully virtual meeting since Jlab is in MEDCON5.
    • Announcement at Production and Analysis meeting.
    • Complete calibrations by April 1? See 2020 Data Production
    • Monitoring Plan
      • Current Monitoring Page
      • Tolga is checking the histograms and procedures for monitoring.
      • Zisis: He would like to be added to the list of monitors. (At a later stage he might pass this on to a new Regina student).
    • PRIMEX work (Karthik)
      • Investigating vertex dependence of pi0 peak. Using geometrical center of target instead of tracking.
      • Checking the following data periods separately: a) He CDC off, b) He CDC on, c) Be CDC off. B=0 for all runs. Removing empty target runs.
      • Mark: For comparison, suggest to process normal GlueX production run using the same procedure as can be used for PRIMEX, i.e. using target geometrical center.
  3. Action Items
  4. Run Updates
    1. FCAL
      • New PDU has been installed that replaces the two previous PDUs (one for the bases; the other for the an agates). However, the remote control for the PDU has not been tested in the field yet. Colin is waiting for a long access to check it out.
      • 1-2 FCAL bases are being replaced per week. About 30-40 bases can be repaired; Nick has taken some home for repair. He will bring them into the lab when ready,
      • FCAL scalers: Group of 16 channels in the FCAL have anomalous pedestals. These channels also have about 1/2 nominal gain. Matt: Could it be that the module was replaced and has the full range at 1 V instead of 2 V. That might explain these anomalies. The module settings should be checked at the next access.
    2. BCAL
      • Log Entry 3806039 BCAL FP#9 is not always present. We have seen this problem before. It appears that the VME pulsing hardware is failing.
      • Sasha: Would like to separate out the FP triggers from the trigger plots and place into FCAL/BCAL sections. Zisis volunteered to do this.
      • There is a new hot channel in the BCAL. Serguei will adjust the pedestal for that channel by hand.
  5. Calibrations
    • FCAL Update (Colin)
    • Sixteen iterations so far showing that pi0 mass and width are converging.
    • The inner and outer 3 layers are excluded. No attempt to calibrate outer 3 layers, where the BCAL shadows the FCAL and no clear pi0 peak is visible.
    • There is about a 1% shift in mass over the course of the first data batch. The pi0 mass is low below run ~71500. Sean: The high intensity (350 nA) data started at 71600, so there may be a rate dependence. Matt: Should investigate the time dependence. Mark: Possibly use one set of gains and adjust (global) non-linear correction to the three different beam current periods.
    • Sasha asked about the capability of the base to handle higher rates. Matt: The increased anode current should be compensated by the active Cockcroft-Walton design
  6. Monitoring
  7. Reconstruction
  8. Efficiencies
  9. Simulations
  10. NIM articles