Meeting Time and Place
Friday March 11, 2011 at 8:15am At Jefferson Lab, the meeting will be held in room ARC 231
Agenda
- ESH&Q minute - Tornado
- Announcements - Budget, Party
- training - ensure up to date
- Manpower
- Solenoid Test Status *
- FDC construction update
- Upcoming work
- FDC practice foils, motion stage, Readiness review, lights
- BCAL Wedges
- Solenoid 3
- Solenoid 2
- Permanent magnets
- Collimator cave - install stands
- Platform - install this summer
Action Items
- Permanent Magnet chambers reworked/leak check chambers
- Remove vacuum chamber and build/install new
- Need to make sure access to BCAL wedges in ESB (Tom)
- Block up existing BCAL boxes
- Move coils 1 and 4 to Hall D
Discussions
- In attendance C. Heck, D. Butler, A. Johnson, T. Carstens, Tim Whitlatch
- Solenoid coil 4 test complete
- Coil 3 leak checking
- Coil 2 Inspections needed
- Double shift starts 21March