**In attendance  C. Heck, D. Butler,  A. Johnson,  T. Carstens,  Tim Whitlatch, S. Speigel, D. Boyles, G. Humble, M. Beizer, B. Bunton, T. Mann, M. Stevens, T. Whitlatch
+
**In attendance  C. Heck, D. Butler,  A. Johnson,  T. Carstens,  Tim Whitlatch, S. Speigel, D. Boyles, G. Humble, M. Beizer, B. Bunton, T. Mann, M. Stevens,  
  
  

Revision as of 09:45, 11 March 2011

Meeting Time and Place

Friday March 11, 2011 at 8:15am At Jefferson Lab, the meeting will be held in room ARC 231

Agenda

  • ESH&Q minute - Tornado
  • Announcements - Budget, Party
    • training - ensure up to date
    • Manpower
  • Solenoid Test Status *
  • FDC construction update
  • Upcoming work
    • FDC practice foils, motion stage, Readiness review, lights
    • BCAL Wedges
    • Solenoid 3
    • Solenoid 2
    • Permanent magnets
    • Collimator cave - install stands
    • Platform - install this summer

Action Items

  • Permanent Magnet chambers reworked/leak check chambers
  • Remove vacuum chamber and build/install new
  • Need to make sure access to BCAL wedges in ESB (Tom)
  • Block up existing BCAL boxes
  • Move coils 1 and 4 to Hall D

Discussions

    • In attendance C. Heck, D. Butler, A. Johnson, T. Carstens, Tim Whitlatch, S. Speigel, D. Boyles, G. Humble, M. Beizer, B. Bunton, T. Mann, M. Stevens,


  • Solenoid coil 4 test complete
  • Coil 3 leak checking
  • Coil 2 Inspections needed
  • Double shift starts 21March