Difference between revisions of "March 13, 2014 Design Meeting"

From GlueXWiki
Jump to: navigation, search
(Created page with "== Meeting Time and Place == Thursday Mar 13, 2014 at 8:15am At Jefferson Lab, room TED 2504 == Agenda == * ESH&Q minute - https://jlabdoc.jlab.org/docushare/dsweb/Get/Docume...")
 
(Agenda)
 
(4 intermediate revisions by the same user not shown)
Line 6: Line 6:
 
== Agenda ==
 
== Agenda ==
 
* ESH&Q minute -  https://jlabdoc.jlab.org/docushare/dsweb/Get/Document-84748
 
* ESH&Q minute -  https://jlabdoc.jlab.org/docushare/dsweb/Get/Document-84748
* Raises - April 15 paycheck, Retroactive to Mar 1, ~2% ave
+
* Raises - April 15 paycheck, Retroactive to Mar 1, ~2.5% ave
 
* Open House May 17 - volunteers needed - Dave Lawrence POC
 
* Open House May 17 - volunteers needed - Dave Lawrence POC
* Lab budgets/schedule
+
* EIC - DOE review - BNL
* Reviews
+
** Good science case -
* Tasks - [[Media:Hall D Tasks mar 2014.pdf]]
+
** ask for more detailed cost and timeline
 +
** Request higher level of R&D
 +
* Hall A should be ready for beam Friday
 +
* Reviews - 12Gev Directors review last week in March, Lehman review 1st week in April - Mostly schedule for Hall D
 +
* Manpower
 +
* Tasks - [[Media:Hall D Tasks mar13 2014.pdf]]
 
* NX
 
* NX
 
* Hall Schedule  [[Media:Hall D Sched Feb 2014.pdf]]
 
* Hall Schedule  [[Media:Hall D Sched Feb 2014.pdf]]
 +
** Solenoid cooldown June?
 +
** FDC install today
 +
** CDC to hall tomorrow
 +
** TOF Install end of March
 +
** Tagger beamline vacuum end of march
 +
** Beam to tagger 1st week in April
 +
** Beam to Hall - Oct 10

Latest revision as of 08:13, 13 March 2014

Meeting Time and Place

Thursday Mar 13, 2014 at 8:15am At Jefferson Lab, room TED 2504

Agenda

  • ESH&Q minute - https://jlabdoc.jlab.org/docushare/dsweb/Get/Document-84748
  • Raises - April 15 paycheck, Retroactive to Mar 1, ~2.5% ave
  • Open House May 17 - volunteers needed - Dave Lawrence POC
  • EIC - DOE review - BNL
    • Good science case -
    • ask for more detailed cost and timeline
    • Request higher level of R&D
  • Hall A should be ready for beam Friday
  • Reviews - 12Gev Directors review last week in March, Lehman review 1st week in April - Mostly schedule for Hall D
  • Manpower
  • Tasks - Media:Hall D Tasks mar13 2014.pdf
  • NX
  • Hall Schedule Media:Hall D Sched Feb 2014.pdf
    • Solenoid cooldown June?
    • FDC install today
    • CDC to hall tomorrow
    • TOF Install end of March
    • Tagger beamline vacuum end of march
    • Beam to tagger 1st week in April
    • Beam to Hall - Oct 10