Line 14: | Line 14: | ||
* Hall A should be ready for beam Friday | * Hall A should be ready for beam Friday | ||
* Reviews - 12Gev Directors review last week in March, Lehman review 1st week in April - Mostly schedule for Hall D | * Reviews - 12Gev Directors review last week in March, Lehman review 1st week in April - Mostly schedule for Hall D | ||
+ | * Manpower | ||
* Tasks - [[Media:Hall D Tasks mar13 2014.pdf]] | * Tasks - [[Media:Hall D Tasks mar13 2014.pdf]] | ||
* NX | * NX |
Latest revision as of 07:13, 13 March 2014
Meeting Time and Place
Thursday Mar 13, 2014 at 8:15am At Jefferson Lab, room TED 2504
Agenda
- ESH&Q minute - https://jlabdoc.jlab.org/docushare/dsweb/Get/Document-84748
- Raises - April 15 paycheck, Retroactive to Mar 1, ~2.5% ave
- Open House May 17 - volunteers needed - Dave Lawrence POC
- EIC - DOE review - BNL
- Good science case -
- ask for more detailed cost and timeline
- Request higher level of R&D
- Hall A should be ready for beam Friday
- Reviews - 12Gev Directors review last week in March, Lehman review 1st week in April - Mostly schedule for Hall D
- Manpower
- Tasks - Media:Hall D Tasks mar13 2014.pdf
- NX
- Hall Schedule Media:Hall D Sched Feb 2014.pdf
- Solenoid cooldown June?
- FDC install today
- CDC to hall tomorrow
- TOF Install end of March
- Tagger beamline vacuum end of march
- Beam to tagger 1st week in April
- Beam to Hall - Oct 10