March 25, 2011 Fab Meeting

From GlueXWiki
Revision as of 09:04, 25 March 2011 by Whitey (Talk | contribs) (Discussions)

(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to: navigation, search

Meeting Time and Place

Friday March 25, 2011 at 8:15am At Jefferson Lab, the meeting will be held in room ARC 231

Agenda

  • ESH&Q minute - Clean and recycle
  • Announcements - Budget
    • training - ensure up to date
    • Manpower
  • Solenoid Test Status *
  • FDC construction update
  • Upcoming work
    • FDC practice foils, motion stage, Readiness review, lights
    • BCAL Wedges
    • Solenoid 3
    • Solenoid 2
    • Permanent magnets
    • Collimator cave - install stands
    • Platform - install this summer

Open Action Items

  • Permanent Magnet chambers reworked/leak check chambers
  • Remove vacuum chamber and build/install new
  • Need to make sure access to BCAL wedges in ESB (Tom)
  • Block up existing BCAL boxes
  • Move coils 1 and 4 to Hall D
  • Test flow switch in Mag field - Scot
  • Tom to work with Jim F. for BCAL readout prototyoe
  • Order remaining controls items for the remaining coils - Scot

New Action Items

  • Hi-pot coil 2 and leak check and insulation

Discussions

    • In attendance C. Heck, D. Butler, A. Johnson, T. Carstens, Tim Whitlatch, S. Speigel, S. Ellis G. Humble, M. Beizer, B. Bunton, T. Mann, M. Stevens,
  • coil 3 in place - need to hi-pot
  • FDC readiness review Thursday
  • good saMPLES FOR UNIDIRECTIONAL CONDUCTIVE TAPE- RIGID FLEX TO CATHODE
  • MANY PROCEDURES WRITTEN
  • April 13 DIS tour - no work in Halld - Need BCAL wedge and solenoid coil
  • LCW flow switch trips at 5G field