Line 16: Line 16:
 
** Coils 1 and 4
 
** Coils 1 and 4
 
** Permanent magnets/DW
 
** Permanent magnets/DW
** Collimator cave - install stands
+
** Collimator cave - install stands - been grouted
 
** Platform - install this summer
 
** Platform - install this summer
  

Revision as of 14:48, 13 May 2011

Meeting Time and Place

Friday May 13, 2011 at 2:30am At Jefferson Lab, the meeting will be held in room ARC 231

Agenda

  • ESH&Q minute - Compressed Air/Gas
  • Announcements -
    • training - ensure up to date SAF110
    • Manpower - Marshal Devendorf starts Monday
  • Solenoid Test Status *
  • FDC construction update
  • Upcoming work
    • BCAL Wedges
    • Solenoid 2 - 2nd shift?
    • Coils 1 and 4
    • Permanent magnets/DW
    • Collimator cave - install stands - been grouted
    • Platform - install this summer

Open Action Items

  • Permanent Magnet chambers reworked/leak check chambers
  • Remove vacuum chamber and build/install new
  • Block up existing BCAL boxes
  • Order remaining controls items for the remaining coils - Scot

New Action Items

  • OSP for ceiling plates

Discussions

    • In attendance C. Heck, D. Butler, A. Johnson, T. Carstens, Tim Whitlatch, S. Speigel, S. Ellis G. Humble, M. Beizer, B. Bunton, T. Mann, M. Stevens,