May 20, 2022 Tech group SAD meeting

From GlueXWiki
Revision as of 13:05, 19 May 2022 by Whitey (Talk | contribs) (Created page with "= Meeting Time and Place == Friday May 20, 2022 10:30am Hall D Counting House and Teams == Agenda == * Safety - Electrical HV * Key validation due this month * Hall will m...")

(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to: navigation, search

Meeting Time and Place =

Friday May 20, 2022 10:30am Hall D Counting House and Teams

Agenda

  • Safety - Electrical HV
  • Key validation due this month
  • Hall will most likely be locked up 2 weeks from today!
  • still no budget to buy FCAL2 stuff
  • Accelerator schedule - HCO in full gear
  • Hall D SAD Tasks
    • CPP INstall Completed
    • PS Parasitic Detectors stages - low priority
    • FCAL Insert Module fabrication
      • 60 brass straps per week needed now?
      • matching mu metal to steel shields
      • cutting tool
      • Moving tent end of June to EEL 108
    • Tagger NMR repair and HCO - Scot
    • Tagger controls/network switch UPS
    • Solenoid HCO - complete
    • Downstream vacuum pipe install - complete - turn pump back on in final HCO
    • Add casters to Microscope stand
  • TEDF work area move in June to test lab high bay or ESB
  • FCAL Insert Drawings - 98% complete
    • need cooling pipe to chiller assy
    • need dark room mod for eelectronic patch panels
    • need to complete 0200 final assy dwg
    • need installation drawing
    • Procurement plan developed
  • New Profiler install - not until August - new plates arrived
  • New 3x3 CCAL for TAC - cabling to be done
  • Tagger Radiator Mod - completeMedia:Fork_mod.pdf
  • DIRC water skid and fiber hookup
  • Controls
    • FDC chiller cooling water flow -
    • FDC start up procedure with set point error - restarted yesterday, any issues?
    • HCO started...
  • General Maintenance
  • On Call - Keith
  • ePAS Training and trial https://www.jlab.org/esh/epas

Action Items

  • Prepare for HCO