Difference between revisions of "May 3, 2011 Readout"
From GlueXWiki
(→Minutes) |
|||
Line 34: | Line 34: | ||
= Minutes = | = Minutes = | ||
− | ''Attending: | + | ''Attending:Beni, Yi, John, Tim, Elton, Eugene (JLab); Will (USM); Andrei (UofR); Christina (Athens) |
# Announcements | # Announcements | ||
+ | #* SiPM First Article arrays have been approved | ||
+ | #* Jlab 6 month shutdown begins in 2 weeks. They plan to connect the accelerator north stub with the tunnel to the tagger hall during this period. | ||
# Review of Action Items | # Review of Action Items | ||
+ | # Monitoring (Christina) | ||
+ | #* MOU signatures should be completed soon | ||
+ | #* Started this week to measure the light distribution in a 1x1x0.15 m3 plexiglass pane to be used to determine how many LEDs will be needed for the Fcal monitoring system. | ||
+ | #* Hope to have some results to present next week at the collaboration meeting. | ||
+ | #* Asked about light guides from USM. The guides are cut but not polished. Need the guides to check the space for boards and cables. | ||
# [http://www.jlab.org/Hall-D/software/wiki/images/d/d1/BCalReadoutReport3May2011.pdf USM update] [http://www.jlab.org/Hall-D/software/wiki/images/8/8e/Morepictures.pdf More Pictures] | # [http://www.jlab.org/Hall-D/software/wiki/images/d/d1/BCalReadoutReport3May2011.pdf USM update] [http://www.jlab.org/Hall-D/software/wiki/images/8/8e/Morepictures.pdf More Pictures] | ||
# SiPM update | # SiPM update |
Revision as of 14:50, 3 May 2011
Teleconference Time: 11:00 a.m. EST
- ESNET 8542553 and EVO session
- JLab Phone: in CC F326 is 757-269-6337 (usual room)
- JLab Phone in CC L207 is 757-269-7084
- Phone in the Regina Videoconference Suite is 306-585-4204
- Athens Phone: in Christina's office is 011-30-210-727-6947
- Phone:
- +1-866-740-1260 : US and Canada
- +1-303-248-0285 : International
- then use participant code: 3421244# (the # is needed when using the phone)
- OR from www.readytalk.com type access code 3421244 into "join a meeting" without the # (you need java plugin)
Contents
Items for followup from previous meeting
-
Check if connections for cooling fluid can be bent radially outward to minimize affect on photons in the gap.Yes. Simulations of impact needed. - Need to get a firm number for the power dissipation in the monitoring control board (in case it is placed inside the housing box)
- SiPM: check cross talk between cells (Yi and Carl)
Documents to Review
Tentative Agenda
- Announcements
- Review of Action Items
- USM update More Pictures
- SiPM update
- Regina Preliminary Tests of Hamamatsu prototype
- Electrical/cooling (Elton)
- Geometry and light guides
- Simulations
Minutes
Attending:Beni, Yi, John, Tim, Elton, Eugene (JLab); Will (USM); Andrei (UofR); Christina (Athens)
- Announcements
- SiPM First Article arrays have been approved
- Jlab 6 month shutdown begins in 2 weeks. They plan to connect the accelerator north stub with the tunnel to the tagger hall during this period.
- Review of Action Items
- Monitoring (Christina)
- MOU signatures should be completed soon
- Started this week to measure the light distribution in a 1x1x0.15 m3 plexiglass pane to be used to determine how many LEDs will be needed for the Fcal monitoring system.
- Hope to have some results to present next week at the collaboration meeting.
- Asked about light guides from USM. The guides are cut but not polished. Need the guides to check the space for boards and cables.
- USM update More Pictures
- SiPM update
- Regina Preliminary Tests of Hamamatsu prototype
- Electrical/cooling (Elton)
- Geometry and light guides
- Simulations