Difference between revisions of "May 7, 2009 Readout"

From GlueXWiki
Jump to: navigation, search
(Reference Documents on DocDB)
Line 23: Line 23:
 
# Light guide work
 
# Light guide work
 
## Regina work: [http://argus.phys.uregina.ca/cgi-bin/private/DocDB/ShowDocument?docid=651 GlueX-doc-651]
 
## Regina work: [http://argus.phys.uregina.ca/cgi-bin/private/DocDB/ShowDocument?docid=651 GlueX-doc-651]
## Indiana work:  
+
## Indiana work: [http://argus.phys.uregina.ca/cgi-bin/private/DocDB/ShowDocument?docid=850 GlueX-doc-850],
### [http://argus.phys.uregina.ca/cgi-bin/private/DocDB/ShowDocument?docid=850 GlueX-doc-850]
+
[http://argus.phys.uregina.ca/cgi-bin/private/DocDB/ShowDocument?docid=1045 GlueX-doc1045]
### [http://argus.phys.uregina.ca/cgi-bin/private/DocDB/ShowDocument?docid=1045 GlueX-doc1045]
+
  
 
= Documents to Review=
 
= Documents to Review=

Revision as of 11:54, 7 May 2009

Teleconference Time: 11:00 a.m. EST

  • EVO session
  • Phone:
    • +1-800-377-8846 : US
    • +1-888-276-7715 : Canada
    • +1-302-709-8424 : International
    • then enter participant code: 00406402# (remember the "#")

Items for followup from previous meeting

  1. Bcal section
    • Zisis will get a quote from Ross machining to find out how much it would cost to polish a segment (both ends)
    • Will will send a shipping address.
  2. JLab to determine how many fibers could be spared now to use in this project.
  3. Elton to determine availability of FM pmts (either from the project for loan) or for purchase from Hamamatsu
  4. Schedule: refinement of schedule by Will with input from Elton and others.

Reference Documents on DocDB

  1. FM PMTs in magnetic field
    1. Athens work: GlueX-doc-712
    2. FIU work: GlueX-doc-1173
  2. Light guide work
    1. Regina work: GlueX-doc-651
    2. Indiana work: GlueX-doc-850,

GlueX-doc1045

Documents to Review

Bcal signal shapes and sizes GlueX-doc-1244

Modeling CNC machine 1

Modeling CNC machine 2

Updated schedule for FM PMT design, from USM

Tentative Agenda

  1. Announcements
  2. Review of Action Items
  3. Preliminary report from USM
  4. Review timeline
    • Materials for prototyping
  5. Bcal signals (Elton)
  6. MOU with USM

Minutes