# Review of Action Items
 
# Review of Action Items
 
# Preliminary report from USM
 
# Preliminary report from USM
 +
#* Updated schedule - Will B.
 +
#* Light collection - Will B.
 +
#* Prototyping planning - Sergey K.
 +
#* Student activities - Alam T.
 +
#* New lab space - Alam T.
 +
#*
 
# Review timeline
 
# Review timeline
 
#*  Materials for prototyping
 
#*  Materials for prototyping

Revision as of 08:59, 7 May 2009

Teleconference Time: 11:00 a.m. EST

  • EVO session
  • Phone:
    • +1-800-377-8846 : US
    • +1-888-276-7715 : Canada
    • +1-302-709-8424 : International
    • then enter participant code: 00406402# (remember the "#")

Items for followup from previous meeting

  1. Bcal section
    • Zisis will get a quote from Ross machining to find out how much it would cost to polish a segment (both ends)
    • Will will send a shipping address.
  2. JLab to determine how many fibers could be spared now to use in this project.
  3. Elton to determine availability of FM pmts (either from the project for loan) or for purchase from Hamamatsu
  4. Schedule: refinement of schedule by Will with input from Elton and others.

Documents to Review

Bcal signal shapes and sizes GlueX-doc-1244

Modeling CNC machine 1

Modeling CNC machine 2

Tentative Agenda

  1. Announcements
  2. Review of Action Items
  3. Preliminary report from USM
    • Updated schedule - Will B.
    • Light collection - Will B.
    • Prototyping planning - Sergey K.
    • Student activities - Alam T.
    • New lab space - Alam T.
  4. Review timeline
    • Materials for prototyping
  5. Bcal signals (Elton)
  6. MOU with USM

Minutes