Difference between revisions of "Mini FCAL Meeting Mon. Mar. 05, 2012"
From GlueXWiki
(Created page with "Minutes FCAL add additional remote scintillator before final Hall B run Kei's working Geant simulations, see http://dustbunny.physics.indiana.edu/~kmoriya/FCALGEANT/ BCAL ...") |
(No difference)
|
Revision as of 14:51, 5 March 2012
Minutes
FCAL
add additional remote scintillator before final Hall B run
Kei's working Geant simulations, see http://dustbunny.physics.indiana.edu/~kmoriya/FCALGEANT/
BCAL
waiting on 1 light guide and the monitoring system to arrive
few simple metal parts to be fabricated
hope to finish detector this week and connect to stand by next week
installation estimate of March 21
scalars will be archived in EPICS
- NEW MEETING TIME ***** MONDAYS AT 1:30 **************