− | Participants: | + | Participants: Fernando, Bill, Al, David, Chris, Glenn, Simon, and Lubomir. |
== Production == | == Production == | ||
− | - | + | - David: Setting up the off-site space: temporary lights were installed, more cabinets to be moved there. Working on the safety papers. The use of Hysol requires eye wash station that will be put in place tomorrow. David will contact the clean room company so that our stuff doesn't interfere with the construction. They will start bringing materials at the beginning of November. We should use the space at the angle of the shelving fences, we have 18' our space (see the sketch linked above). |
+ | |||
+ | - We get 5 wire frames each week and send another 5 laminated with the Rohacell rings, back for fly cut. For now 10 wire frames were laminated. | ||
- Five wire frames were laminated with Rohacell rings and sent back to the company for flat cut. Last two laminated at Blue Crab. Five new frames will come soon. Two new Rohacell rings are ready. | - Five wire frames were laminated with Rohacell rings and sent back to the company for flat cut. Last two laminated at Blue Crab. Five new frames will come soon. Two new Rohacell rings are ready. |
Revision as of 17:04, 21 October 2010
October 21, 2010 FDC meeting
Tentative Agenda
- Production (David)
- Electronics (Fernando, Chris, Roger)
- Update on PCBs
- Cathode foil and rigid-flex procurement [1]
- Engineering (Bill, David)
- Wire stringing
- Gluing and soldering materials
- Full-scale prototype tests (Lubomir)
- gas mixture studies FDC Log Book, page 526
- Other