Difference between revisions of "Minutes-10-7-2010"

From GlueXWiki
Jump to: navigation, search
Line 30: Line 30:
 
- There was a meeting between JLab people and AdvanceTEC that will build the clean room. Completion date: January 7th. AdvanceTEC had two concerns: the power coming to building (from Dominion Power) is close to the expected use and has to be checked. The second is related to the quality of the floor, not good enough for 10K clean room. AdvanceTEC will send a quote to re-seal the floor.  
 
- There was a meeting between JLab people and AdvanceTEC that will build the clean room. Completion date: January 7th. AdvanceTEC had two concerns: the power coming to building (from Dominion Power) is close to the expected use and has to be checked. The second is related to the quality of the floor, not good enough for 10K clean room. AdvanceTEC will send a quote to re-seal the floor.  
  
- Bill, David and a machinist  
+
- Bill, David and a machinist from our machine shop visited
 
    
 
    
 
== Electronics ==
 
== Electronics ==

Revision as of 16:19, 7 October 2010

October 7, 2010 FDC meeting

Tentative Agenda

  1. Production
    • Blue Crab status
    • Frame production
  2. Electronics
    • Update on PCBs, fADC125 and other (Fernando, Chris, Gerard)
  3. Engineering
    • Wire stringing: fixtures, movement system (Bill, David)
    • Update on tension measurements (Lubomir)
    • Wire tension requirements (Lubomir)
    • Other: gas system using methane
  4. Full-scale prototype
  5. Other