= Minutes =
 
= Minutes =
Participants: Eugene, Bill, Glenn, Simon, Chris, Roger, David, Beni, and Lubomir.
+
Participants: Eugene, Fernando, Bill, Casey, Mark, Chris, Roger, Simon, Beni, and Lubomir.
  
 
== Production ==
 
== Production ==
  
- The company will start bringing materials for the clean room on Nov 24. The AC for the whole area will be installed by Dec 7. Before that for the lamination we will use mostly the office (low humidity <40%), and the granite tables outside for vacuum bagging if the humidity is low. That was not the case today.
+
- They are going to install phones and work on the Internet today at Blue Crab. We can now use heaters at low temperatures; must be above 60degF for gluing.  
  
- We got all the wire frames (32) and spacer rings (30). 17 wire frames laminated; 14 are back at Vision machine for fly cut.  
+
- By next Wednesday expect to have all the wire frames laminated. 18 frames came back from Vision machine after fly cut. They started there also the cathode frame production.
 +
 
 +
- Dave made the next version of the production plan. We start production in March 2011, the first package will be ready by September 2011 and then every ~4 months we plan to have a new package. According to the plan we will produce chamber by chamber serially, so that we can test them at the same time.
  
 
== Electronics ==
 
== Electronics ==
  
 +
<!--
 
- Chris: by Wednesday we will have all the PCBs populated. The company sent two pictures (link above) showing delaminations on two of the boards. They claim the delamination was there when the boards arrived. But Chris would have seen it!? Roger: the heating cycle they use may cause delamination. Chris will ask
 
- Chris: by Wednesday we will have all the PCBs populated. The company sent two pictures (link above) showing delaminations on two of the boards. They claim the delamination was there when the boards arrived. But Chris would have seen it!? Roger: the heating cycle they use may cause delamination. Chris will ask
 
the company for information about this.  
 
the company for information about this.  

Revision as of 18:15, 11 November 2010

November 11, 2010 FDC meeting

Tentative Agenda

  1. Production (David)
    • Blue Crab status sketch
    • Frame lamination
    • Production plan
  2. Electronics (Fernando, Chris, Roger)
    • Update on PCB inspection
    • Other
    • Cathode foil production
    • Rigid-flex procurement
  3. Engineering (Bill, David, Beni)
    • Wire stringing status model ; stepper motor controller.
    • Other
  4. Full-scale prototype tests
  5. Other


Minutes

Participants: Eugene, Fernando, Bill, Casey, Mark, Chris, Roger, Simon, Beni, and Lubomir.

Production

- They are going to install phones and work on the Internet today at Blue Crab. We can now use heaters at low temperatures; must be above 60degF for gluing.

- By next Wednesday expect to have all the wire frames laminated. 18 frames came back from Vision machine after fly cut. They started there also the cathode frame production.

- Dave made the next version of the production plan. We start production in March 2011, the first package will be ready by September 2011 and then every ~4 months we plan to have a new package. According to the plan we will produce chamber by chamber serially, so that we can test them at the same time.

Electronics