November 11, 2010 FDC meeting

Tentative Agenda

  1. Production (David)
    • Blue Crab status sketch
    • Frame lamination
    • Production plan
  2. Electronics (Fernando, Chris, Roger)
    • Update on PCB inspection
    • Other
    • Cathode foil production
    • Rigid-flex procurement
  3. Engineering (Bill, David, Beni)
    • Wire stringing status model ; stepper motor controller.
    • Other
  4. Full-scale prototype tests
  5. Other


Minutes

Participants: Eugene, Fernando, Bill, Casey, Mark, Chris, Roger, Simon, Beni, and Lubomir.

Production

- They are going to install phones and work on the Internet today at Blue Crab. We can now use heaters at low temperatures; must be above 60degF for gluing.

- By next Wednesday expect to have all the wire frames laminated. 18 frames came back from Vision machine after fly cut. They started there also the cathode frame production.

- Dave made the next version of the production plan. We start production in March 2011, the first package will be ready by September 2011 and then every ~4 months we plan to have a new package. According to the plan we will produce chamber by chamber serially, so that we can test them at the same time.

Electronics