== Production ==
 
== Production ==
  
- Dave: now working on package #2.  
+
- Dave: now that the techs are back we are working on package #2. Tina and Mike are cutting/gluing new foils; Anatoly tested already the three foil sets that we have received.   
  
 
- On package #1 Vlad installed the ground connection before
 
- On package #1 Vlad installed the ground connection before

Revision as of 16:07, 29 November 2012

November 29, 2012 FDC meeting

Agenda

  1. Production Construction Tracking (Dave)
    • Package #1 subsystems
    • Package #2 production
    • Package #4 testing (Vlad)
  2. Corrosion tests (Vlad)
  3. Engineering
  4. Electronics (Chris, Nick)
  5. Tests at EEL126 (Lubomir)
    • Third package wire resolution FDC E-log
    • Plans for testing packages #1 and #4
  6. Other