- Dave: now the techs are back and we are working on package #2. Tina and Mike are cutting/gluing new foils; Anatoly tested already the six new foil sets that we have received. Anatoly started gluing the daughter cards on the cathodes that were done before. Priority is to finish the two type-3 cathodes that will be needed in any package configuration.
 
- Dave: now the techs are back and we are working on package #2. Tina and Mike are cutting/gluing new foils; Anatoly tested already the six new foil sets that we have received. Anatoly started gluing the daughter cards on the cathodes that were done before. Priority is to finish the two type-3 cathodes that will be needed in any package configuration.
  
- On package #1 Vlad installed the ground connections before Thanksgiving, then this week we installed the cooling loops and yesterday Chris and Nick started working on the HV cabling. The package will be ready at the beginning of the next week. We decided not to install the cooling manifolds so far: we don't need them now and in case we need to open the package we will not be able to re-use the cooling tubes.   
+
- On package #1 Vlad installed the ground connections before Thanksgiving, then this week we installed the cooling loops and yesterday Chris and Nick started working on the HV cabling. The package will be ready at the beginning of the next week. We decided not to install the cooling manifolds so far: we don't need them now and in case we need to open the package we will not be able to re-use the cooling tubes. On package #3 it turned out the splittings of the cooling tubes are in wrong places due to misinterpreting the drawings. Correcting this will take ~2 days but will do it later.   
  
- Package #4 was assembled just before Thanksgiving  
+
- Package #4 was assembled (the two missing cells) just before Thanksgiving and flushed with gas over the holidays: now oxygen is 151ppm. Vlad tested all the cells, not only the last two. Currents on cells from #6 to #2: 21/-3, 44/-4, 42/-3, 50/-3, 110/-100 nA. On cell#1 HV could be applied only to several HV sectors +/-HV1, +/-HV4, and +HV3. On the rest of the HV sectors we found shorts between the HV and the lower cathode and therefore we opened it today: as expected we found a broken wire, field 47. It is not clear when and how the wire broke. Certainly it was in place when the wire frame was installed in the package, but later after closing the package somehow it broke in the middle, the only explanation so far that it may have had a kink in this place (Casey). Also some wire frame deformation must be involved, say even on the pins it stayed deformed but after tightening the package got flat and the wire broke? The tension of the wire was 122g very close to its neighbors.     
  
  
Line 36: Line 36:
 
== Engineering ==
 
== Engineering ==
  
- Bill: the new SMC chiller and the fluorinert will come middle of December, finished the documentation for the pressure system, discussed with Ron Bartek the power for the chiller in 126. The chiller requires also colling with water, still not clear how to do this.
+
- Without Bill not much to say.
 
+
- AC at 126: As Eugene suggested it's not worth investing in Blue Crab, so we will do the tests at 126. Before it was proposed to install two ceiling fans, but then a cheaper solution was found: two split cooling units. Bill after the meeting: the reqs for the units are out, expect to install them before Christmas.
+
 
+
- FDC installation. The FDC installation cart is already at Blue Crab. First, it has to surveyed and the rail adjusted. All the packages will be installed on the cart at Blue Crab and surveyed there. We don't know when we will finish the complete tests of the packages; it depends on the fADC125 availability. Eugene: we can bring the FDC to the Hall middle of July 2013 and will have time for installation/testing till the end of October. What has to be done there: once more FDC survey (few days), cable installation (two weeks at least excluding testing of the connectivity), installation of/connection to the gas, cooling, HV, LV systems (two weeks), testing/troubleshooting/ground improvements (at least a month, maybe two). Will need to have all the electronics, DAQ system working by that time. Will have to install several scintillator pedals for cosmic triggering.
+
  
 
== Electronics ==
 
== Electronics ==

Revision as of 17:21, 29 November 2012

November 29, 2012 FDC meeting

Agenda

  1. Production Construction Tracking (Dave)
    • Package #1 subsystems
    • Package #2 production
    • Package #4 testing (Vlad)
  2. Corrosion tests (Vlad)
  3. Engineering
  4. Electronics (Chris, Nick)
  5. Tests at EEL126 (Lubomir)
    • Third package wire resolution FDC E-log
    • Plans for testing packages #1 and #4
  6. Other