Line 19: | Line 19: | ||
== Production == | == Production == | ||
− | - Dave for the spare parts: wire frame #3 (old) was tested without HV caps (580/-50nA at 2100/-500V) and now | + | - Dave for the spare parts: wire frame #3 (old) was tested without HV caps (580/-50nA at 2100/-500V) and now Anatoly is soldering them. Last wire frame (#32) was strung by Casey and Dave, Casey is gluing the wires now, tomorrow will come soldering and tension measurements. Don't need to convert type-2 to type-1 cathode frame (mill the O-ring groove) we have enough; the one that was deformed was used and looks OK. No need for extra spacer rings, the ones on the full-scale prototype can be used (Bill). Tina will come over the weekend to work on the last cathodes. Expect to finish with the spare part production in March. |
− | - Lubomir for package #2: | + | - Lubomir for package #2: completely tested, oxygen went down to 170ppm. Started installing the grounding, 75% done - will be ready tomorrow. It is now on the mounting table |
− | + | and we don't have extra strong-back to put it on a table, or we can't use the holding brackets. | |
− | + | ||
- Started testing some of the very old wire frames (W003 and W006) in a separate set-up with two Lexan sheets and a spacer ring. We need just one of them to be holding HV to have 6 spares. | - Started testing some of the very old wire frames (W003 and W006) in a separate set-up with two Lexan sheets and a spacer ring. We need just one of them to be holding HV to have 6 spares. |
Revision as of 18:07, 14 February 2013
February 14, 2013 FDC meeting
Agenda
- Production Construction Tracking (Dave)
- Basis of Estimate for the FDC activities (Lubomir, Bill, Dave)
- Corrosion tests at MePhi latest results (Lubomir)
- Engineering (Bill)
- Electronics (Chris, Nick)
- Tests at EEL126 FDC E-log (Beni)
- Other