Line 19: Line 19:
 
== Production ==
 
== Production ==
  
- Dave for the spare parts: wire frame #3 (old) was tested without HV caps (580/-50nA at 2100/-500V) and now Anatly is soldering them. Last wire frame (#32) was strung by Casey and Dave, Casey is gluing the wires now, tomorrow will come soldering and tension measurements.  
+
- Dave for the spare parts: wire frame #3 (old) was tested without HV caps (580/-50nA at 2100/-500V) and now Anatoly is soldering them. Last wire frame (#32) was strung by Casey and Dave, Casey is gluing the wires now, tomorrow will come soldering and tension measurements. Don't need to convert type-2 to type-1 cathode frame (mill the O-ring groove) we have enough; the one that was deformed was used and looks OK. No need for extra spacer rings, the ones on the full-scale prototype can be used (Bill). Tina will come over the weekend to work on the last cathodes. Expect to finish with the spare part production in March.
  
- Lubomir for package #2: despite replacing sense wire 37 on W010 (second cell), it showed a noise this time very close to the HV end (Down strip #15, Upper strip #3). On Monday we opened the package for a fourth time. During this operation, an O-ring with Apizon fell at the periphery of the top cell wire plane (W012) close to the signal side in the region of wire #76-89. Casey cleaned it with alcohol and later we checked this place with a source: no difference in the signals found. We put W010 on the stringing table and looked with the web-camera at the "noisy" place. There were some balls on the one of the field wires next to sense 37 and we cleaned it (applying some pressure with q-tips on both sides of the wire). We installed w012 in the second cell and put w010 on the top, just in case we have to open it again. This time the noise disappeared; all the channels that were re-installed were tested again and all are working fine. Next week we will continue with the ground installation.
+
- Lubomir for package #2: completely tested, oxygen went down to 170ppm. Started installing the grounding, 75% done - will be ready tomorrow. It is now on the mounting table
 
+
and we don't have extra strong-back to put it on a table, or we can't use the holding brackets.
- Additional parts to build one spare package: we realized we can re-use two spacer rings from the full-scale prototype and don't have to order them ($1.6k). Bill will look at the drawings to confirm this. They don't have guage holes but can be drilled. Bill got a quotation for the two 35mm spacer rings (to test the helium drift chamber concept) at about the same $1.6k. We will submit one PR for all the parts.
+
  
 
- Started testing some of the very old wire frames (W003 and W006) in a separate set-up with two Lexan sheets and a spacer ring. We need just one of them to be holding HV to have 6 spares.
 
- Started testing some of the very old wire frames (W003 and W006) in a separate set-up with two Lexan sheets and a spacer ring. We need just one of them to be holding HV to have 6 spares.

Revision as of 18:07, 14 February 2013

February 14, 2013 FDC meeting

Agenda

  1. Production Construction Tracking (Dave)
  2. Basis of Estimate for the FDC activities (Lubomir, Bill, Dave)
  3. Corrosion tests at MePhi latest results (Lubomir)
  4. Engineering (Bill)
  5. Electronics (Chris, Nick)
  6. Tests at EEL126 FDC E-log (Beni)
  7. Other