Difference between revisions of "Minutes-3-18-2010"

From GlueXWiki
Jump to: navigation, search
(Tentative Agenda)
Line 7: Line 7:
 
#* production space update
 
#* production space update
 
#* FDC procurement plans
 
#* FDC procurement plans
 +
#** procurement of cables, connectors (HV, signal, LV)
 +
#** procurement of cathodes: flex connection, beam hole size [http://www.jlab.org/Hall-D/detector/fdc/new_reports/ wire sample reports]
 
# Full scale prototype tests
 
# Full scale prototype tests
 
#* prototype test updates
 
#* prototype test updates
Line 14: Line 16:
 
# Wire frame update
 
# Wire frame update
 
#* PCB status
 
#* PCB status
#* wire sample measurements [http://www.jlab.org/Hall-D/detector/fdc/new_reports/ wire sample reports]
+
#* wire sample measurements [http://www.jlab.org/Hall-D/detector/fdc/new_reports/ tracking meeting]
 
# Cathode frame redesign
 
# Cathode frame redesign
 
#* cathode redesign status
 
#* cathode redesign status

Revision as of 18:34, 17 March 2010

March 18, 2010 FDC meeting

Tentative Agenda

  1. FDC production
    • production space update
    • FDC procurement plans
      • procurement of cables, connectors (HV, signal, LV)
      • procurement of cathodes: flex connection, beam hole size wire sample reports
  2. Full scale prototype tests
    • prototype test updates
    • HV tests
    • frame modification work: cathode sandwich and wire frame
    • plans for layer 3
  3. Wire frame update
  4. Cathode frame redesign
    • cathode redesign status
    • rigid-flex assembly
  5. Wire winding
    • IUCF phase 3 contract
    • plans for wire winding upgrades
    • tension specs
  6. Other
    • FDC naming convention
    • ...