Difference between revisions of "Minutes-3-25-2010"

From GlueXWiki
Jump to: navigation, search
m (Text replacement - "http://argus.phys.uregina.ca/cgi-bin/private" to "https://halldweb.jlab.org/doc-private")
 
(11 intermediate revisions by one other user not shown)
Line 1: Line 1:
 +
 +
 
March 25, 2010 FDC meeting
 
March 25, 2010 FDC meeting
  
Line 17: Line 19:
 
# Full scale prototype tests
 
# Full scale prototype tests
 
#* lessons learned from the HV tests [[Media:wire_signal_issues.pdf | cope-shots1]], [[Media:wire_signal_issues1.pdf | cope-shots2]], [http://www.jlab.org/Hall-D/detector/fdc/pictures/ HV issues]
 
#* lessons learned from the HV tests [[Media:wire_signal_issues.pdf | cope-shots1]], [[Media:wire_signal_issues1.pdf | cope-shots2]], [http://www.jlab.org/Hall-D/detector/fdc/pictures/ HV issues]
#* plans for tests in the tend
+
#* plans for tests in the tent
 
#* some results from the tests with Sr source [http://www.jlab.org/Hall-D/detector/fdclog/ FDC Log Book] (Lubomir)
 
#* some results from the tests with Sr source [http://www.jlab.org/Hall-D/detector/fdclog/ FDC Log Book] (Lubomir)
 
# Cathode frame redesign
 
# Cathode frame redesign
Line 31: Line 33:
 
= Production space update =
 
= Production space update =
  
Two options are being considered. Properties behind Office Depot (preferably "Minuteman Press") and properties around Middle Ground Blvd (at Blue Crab) . The rent price of the latter is half the one at Office Depot, but requires building  
+
Two options are being considered: properties behind Office Depot (preferably "Minuteman Press"), and properties around Middle Ground Blvd (at Blue Crab) . The rent price of the latter is half the one at Office Depot, but requires building  
a room inside the bay area.  Our position is that he most promising for FDC construction that needs only minimal modifications is the "Minuteman press". We can share the bay area with SRF (John Hogan).   
+
a room inside the bay area.  Our position is that the most promising for FDC construction that needs only minimal modifications is the "Minuteman press". We can share the bay area there with SRF (John Hogan).   
  
== Electronics ==
+
= Electronics =
  
- Fernando presented measurements comparing the discriminator part of the pre-amp cards. The worst card so far is showing ~30% variations (min - max range). The question was whether this is acceptable. We all agreed that we don't want to modify the design of the cards.  
+
- Fernando presented measurements of the discriminator part of the pre-amp cards. The worst card so far is showing ~30% variations (min - max range) in the effective threshold, among the 3x8 channels. The question was whether this is acceptable. We all agreed that we don't want to modify the present design of the cards. The variations of the detector response are expected to be compatible if not bigger than 30%. The only procedure that may be considered if possible, is sorting the ASICs before putting them on the cards. 
  
<!--
+
- Next week the design of the PCBs will be finalized (Fernando, Kim, Dan) and posted on the web. We discussed also the option of having checking points on the sense wire resistors at the readout side, related to the problems with the resistors discussed later.
  
- Next week the design of the PCBs will be finalized (Fernando, Kim, Dan) and posted on the web. We discussed also the option of having checking points on the resistors at the   
+
= Frame modification =
  
- Tim organized a visit to off-site properties (across the street) that could be used
+
- The one-piece-g10 frame came back from the shop ready to be glued to the PCB ring, the latter is in the shop.
for FDC production/storage purposes. We are considering this as a possible option that needs to be further investigated. There was a second meeting after this one, discussing the requirements to use the space for the FDC production.  
+
  
- Fernando is working on the procurement of the HV and signal cables/connectors. He wants to make sure the lengths of the cables corresponds to the up-to-date plans.  
+
- Chamber 3 was tested for leakage through the ground plane, using a sniffer at the cathode side gas holes. Once more, the leakage was confirmed. Same test will be performed with chamber 2.
  
- procurement of the cathodes: Roger and Dan are finalizing the cathode modifications. Eugene suggested to investigate the failure rate in soldering the flexes. Another showstopper is the decision about the size of the hole of the cathode strips. This issue was discussed during the last tracking meeting and Alex will investigate the effect of the copper material on the detector rates. We aim to have the same hole size on all the FDC packages. Fortunately, the decision about the the size of the wire deadening area that defines the sensitive area of the chamber, can be done later.
+
=  Wire winding update =
  
== Full scale prototype tests ==
+
- Dan informed us about the latest IUCF budget estimate for phase 3 including the wire winding upgrades. This and other topics related to the transfer of responsibilities from Dan will be discussed in a separate meeting on Monday.
  
- Beni finished the tests with Sr source, the prototype was moved back in the tent and the top layer was opened.
+
- The specifications for the wire tension will be revisited at the next meeting (Lubomir) 
  
- Beni summarized the results of the plateau and drift time investigations with different gas mixtures. So far there's nothing unexpected. Nevertheless, there are concerns about the uniformity of the detector response and the quality of the gas inside the chambers. Systematic analysis of the full scale prototype tests will be prepared for the next meeting. Lubomir showed results from the tests with 55Fe: the energy resolution is about 7%. 
+
= Full scale prototype tests =
  
- At the end of the testing, Beni made a series of HV studies with CO2 only. Before and after opening the chamber he repeated the same tests. At all of the sectors, except maybe few, he was able to reach much higher HV than with Ar - CO2 mixtures.
+
- Several sources of the HV problems we had during the testing were identified:
  
- We observed corona discharge (bluish light barely visible in the darkened tent) at several places in one HV sector (at about +2700V/-400V) of the opened top chamber. The light was visible on the soldering pad of the last (for the sector) sense wire, later along the whole wire, and then on all the wires in that sector. Also we saw different spots blinking for few seconds coming from some dust on the wires. The corona discharge requires conductivity between places with different potential (through the air, or on the board) but is visible at places like edges or thin wires with very high electric field.  
+
1. We found inside chamber 1 some metal pieces, like a wire piece, probably from the green cables used for grounding. Bill and Mark discussed how to avoid this.  
  
- All this suggests that so far there are no indications that the HV problems are related to the boards, except maybe at few places due to impurities. The dust on the wires could explain at least some of the HV problems we had during the test. Dan suggested to clean the wires with alcohol and ionized nitrogen and continue the HV tests.  
+
2. The corona discharge we observed on the PCBs (at the readout side) was obviously causing some of the problems. It turned out that cleaning of the boards with alcohol helped. Probable explanation is that there are impurities in the epoxy (from the wire frame production) which combined with some impurities on the surface of the boards would create the discharge.  
   
+
- Bill informed us about the frame modification work: the one-piece g10 wire frame came from the shop and Casey and Mark are working on the frames. The work will continue next week.
+
  
== Wire frame update ==
+
3. On one of the boards we found sparking at the card connector. By looking at the pins that were sparking (in dark) we identified the corresponding channels. Replacing two sense wire resistors solved the problem. Possible explanation is that the resistor contacts were damaged when handling the frames.
  
- Fernado is reviewing the modified PCBs, waiting also the diagnosis of the HV problems
+
- After fixing the above problems on chamber 1 we were able to set the HV at 2200V with 60/40 Ar/C02 gas mixture on all sectors.
  
- new wire sample measurements were posted
+
- Beni informed us about the tests he performed inside the tent with chamber 1. Using a scope he looked channel by channel at the signals (cosmics) from the pre-amps on the wires. He found that about 10% of the channels show high rate signals with amplitudes up to 300mV. These signals would disappear if lowering the HV.
  
== Wire winding ==
+
- The plan is to perform such tests for each chamber in the tent as being more efficient, possibly also using DAQ. We also plan to open chamber 1 and try to clean the corresponding wires.
  
- Keith Solberg is reviewing the plans for wire winding upgrades prepared by Bill
+
= Cathode frame design =
  
- Lubomir suggested to measure the capacitance of one wire, which parameter enters in the calculations of the tension specs. Fernando can provide a capacitance meter.
+
- Alex presented his MC results investigating the size of the hole for the beam. Two separate effects have been studied.  
  
- Brian suggested to investigate the aging of the wire deadening. In this line, Eugene mentioned that the weight of the copper in that area should also be taken into account when calculating the tension specs.  
+
1. The first one is the background created by the copper material on the cathodes. No change of the background within the statistics used, was observed when reducing the cathode hole size from the "standard" 2.3, 3.2, 3.9 4.6 cm radius for FDC1, ..., FDC4 to 1.3cm for all the packages. 1.3cm radius is small enough to insure high efficiency for hits with radial distance  > 2.3cm as in the standard hole size. The thickness of the copper material (in radiation lengths) is ~20% of the target thickness. This means that the maximum increase of the background (without any hole at the cathodes) will be 20%. So, in principle it is possible to make the hole radius even smaller that 1.3cm.
  
 +
2. The second effect studied, was the occupancies on the strips related to the size of the sensitive area. The latter is defined by the size of the wire deadening area and fortunately we can make a decision about this size later. Based on the strip rates, Alex suggested 3.0, 3.0, 3.9, 3.9 cm radius for the holes in the wire planes for the FDC1,.., FDC4 packages. The advantage would be that we will have two pairs of equal packages. Further investigations with MC using tracking are needed.
  
== Other ==
+
= Other =
 
+
- Lubomir prepared a short description of the FDC naming convention. There were several suggestions to improve the convention. A modified version will be ready for the next meeting.
+
  
 +
- Bill proposed for the future meetings to have the physics discussions scheduled at the end of the meeting. Lubomir will try to better separate  the engineering/organizational topics from the physics ones when scheduling the future meetings.     
  
 +
<!--
  
  
Line 110: Line 110:
 
==Prototype Testing==
 
==Prototype Testing==
 
   - The current version of the full-scale prototype test plan is on the
 
   - The current version of the full-scale prototype test plan is on the
     GlueX portal as ([http://argus.phys.uregina.ca/cgi-bin/private/DocDB/ShowDocument?docid=1304 GlueX-doc-1304]).
+
     GlueX portal as ([https://halldweb.jlab.org/doc-private/DocDB/ShowDocument?docid=1304 GlueX-doc-1304]).
  
 
   - Two layer test update: See the [http://www.jlab.org/Hall-D/detector/fdclog/ FDC Log Book] for updates on the continuing work.
 
   - Two layer test update: See the [http://www.jlab.org/Hall-D/detector/fdclog/ FDC Log Book] for updates on the continuing work.

Latest revision as of 17:14, 24 February 2017


March 25, 2010 FDC meeting


Tentative Agenda

  1. Production space update off-site floor plans
  2. Electronics
    • threshold variations in the discriminator section of the pre-amps (Fernando) Fernando's pdf
    • PCB status
  3. Frame modification
    • cathode sandwich and wire frame
    • ground plane tests (leakage, tension)
  4. Wire winding update
    • IUCF phase 3 contract phase 3 budget
    • plans for wire winding upgrades in the summer
    • tension specs
  5. Full scale prototype tests
  6. Cathode frame redesign
  7. Other

Minutes

Participants: Lubomir, Eugene, Bill, Daniel, Glenn, Casey, Mark, Beni, Simon, Fernando

Production space update

Two options are being considered: properties behind Office Depot (preferably "Minuteman Press"), and properties around Middle Ground Blvd (at Blue Crab) . The rent price of the latter is half the one at Office Depot, but requires building a room inside the bay area. Our position is that the most promising for FDC construction that needs only minimal modifications is the "Minuteman press". We can share the bay area there with SRF (John Hogan).

Electronics

- Fernando presented measurements of the discriminator part of the pre-amp cards. The worst card so far is showing ~30% variations (min - max range) in the effective threshold, among the 3x8 channels. The question was whether this is acceptable. We all agreed that we don't want to modify the present design of the cards. The variations of the detector response are expected to be compatible if not bigger than 30%. The only procedure that may be considered if possible, is sorting the ASICs before putting them on the cards.

- Next week the design of the PCBs will be finalized (Fernando, Kim, Dan) and posted on the web. We discussed also the option of having checking points on the sense wire resistors at the readout side, related to the problems with the resistors discussed later.

Frame modification

- The one-piece-g10 frame came back from the shop ready to be glued to the PCB ring, the latter is in the shop.

- Chamber 3 was tested for leakage through the ground plane, using a sniffer at the cathode side gas holes. Once more, the leakage was confirmed. Same test will be performed with chamber 2.

Wire winding update

- Dan informed us about the latest IUCF budget estimate for phase 3 including the wire winding upgrades. This and other topics related to the transfer of responsibilities from Dan will be discussed in a separate meeting on Monday.

- The specifications for the wire tension will be revisited at the next meeting (Lubomir)

Full scale prototype tests

- Several sources of the HV problems we had during the testing were identified:

1. We found inside chamber 1 some metal pieces, like a wire piece, probably from the green cables used for grounding. Bill and Mark discussed how to avoid this.

2. The corona discharge we observed on the PCBs (at the readout side) was obviously causing some of the problems. It turned out that cleaning of the boards with alcohol helped. Probable explanation is that there are impurities in the epoxy (from the wire frame production) which combined with some impurities on the surface of the boards would create the discharge.

3. On one of the boards we found sparking at the card connector. By looking at the pins that were sparking (in dark) we identified the corresponding channels. Replacing two sense wire resistors solved the problem. Possible explanation is that the resistor contacts were damaged when handling the frames.

- After fixing the above problems on chamber 1 we were able to set the HV at 2200V with 60/40 Ar/C02 gas mixture on all sectors.

- Beni informed us about the tests he performed inside the tent with chamber 1. Using a scope he looked channel by channel at the signals (cosmics) from the pre-amps on the wires. He found that about 10% of the channels show high rate signals with amplitudes up to 300mV. These signals would disappear if lowering the HV.

- The plan is to perform such tests for each chamber in the tent as being more efficient, possibly also using DAQ. We also plan to open chamber 1 and try to clean the corresponding wires.

Cathode frame design

- Alex presented his MC results investigating the size of the hole for the beam. Two separate effects have been studied.

1. The first one is the background created by the copper material on the cathodes. No change of the background within the statistics used, was observed when reducing the cathode hole size from the "standard" 2.3, 3.2, 3.9 4.6 cm radius for FDC1, ..., FDC4 to 1.3cm for all the packages. 1.3cm radius is small enough to insure high efficiency for hits with radial distance > 2.3cm as in the standard hole size. The thickness of the copper material (in radiation lengths) is ~20% of the target thickness. This means that the maximum increase of the background (without any hole at the cathodes) will be 20%. So, in principle it is possible to make the hole radius even smaller that 1.3cm.

2. The second effect studied, was the occupancies on the strips related to the size of the sensitive area. The latter is defined by the size of the wire deadening area and fortunately we can make a decision about this size later. Based on the strip rates, Alex suggested 3.0, 3.0, 3.9, 3.9 cm radius for the holes in the wire planes for the FDC1,.., FDC4 packages. The advantage would be that we will have two pairs of equal packages. Further investigations with MC using tracking are needed.

Other

- Bill proposed for the future meetings to have the physics discussions scheduled at the end of the meeting. Lubomir will try to better separate the engineering/organizational topics from the physics ones when scheduling the future meetings.