Line 16: Line 16:
 
#* tension specs
 
#* tension specs
 
# Full scale prototype tests
 
# Full scale prototype tests
#* lessons learned from the HV tests [[Media:wire_signal_issues.pdf | cope-shots1]], [[Media:wire_signal_issues1.pdf | cope-shots2]]
+
#* lessons learned from the HV tests [[Media:wire_signal_issues.pdf | cope-shots1]], [[Media:wire_signal_issues1.pdf | cope-shots2]], [http://www.jlab.org/Hall-D/detector/fdc/pictures/DSC04132.eps HV issues]
 
#* plans for tests in the tend
 
#* plans for tests in the tend
 
#* some results from the tests with Sr source [http://www.jlab.org/Hall-D/detector/fdclog/ FDC Log Book] (Lubomir)
 
#* some results from the tests with Sr source [http://www.jlab.org/Hall-D/detector/fdclog/ FDC Log Book] (Lubomir)

Revision as of 12:08, 25 March 2010

March 25, 2010 FDC meeting


Tentative Agenda

  1. Production space update off-site floor plans
  2. Electronics
    • threshold variations in the discriminator section of the pre-amps (Fernando)
    • PCB status
  3. Frame modification work
    • cathode sandwich and wire frame
    • ground plane tests (leakage, tension)
  4. Wire winding update
    • IUCF phase 3 contract phase 3 budget
    • plans for wire winding upgrades in the summer
    • tension specs
  5. Full scale prototype tests
  6. Cathode frame redesign
    • MC studies of the beam hole size (Alex)
  7. Other