Tentative Agenda

  1. Production space update off-site floor plans
  2. Electronics
    • threshold variations in the discriminator section of the pre-amps (Fernando) Fernando's pdf
    • PCB status
  3. Frame modification
    • cathode sandwich and wire frame
    • ground plane tests (leakage, tension)
  4. Wire winding update
    • IUCF phase 3 contract phase 3 budget
    • plans for wire winding upgrades in the summer
    • tension specs
  5. Full scale prototype tests
  6. Cathode frame redesign
  7. Other

Minutes

Participants: Lubomir, Eugene, Bill, Daniel, Glenn, Casey, Mark, Beni, Simon, Fernando

Production space update

Two options are being considered. Properties behind Office Depot (preferably "Minuteman Press") and properties around Middle Ground Blvd (at Blue Crab) . The rent price of the latter is half the one at Office Depot, but requires building a room inside the bay area. Our position is that he most promising for FDC construction that needs only minimal modifications is the "Minuteman press". We can share the bay area with SRF (John Hogan).

Electronics

- Fernando presented measurements comparing the discriminator part of the pre-amp cards. The worst card so far is showing ~30% variations (min - max range). The question was whether this is acceptable. We all agreed that we don't want to modify the design of the cards.