April 8, 2010 FDC meeting


Tentative Agenda

  1. Production
    • Update on the off-site production space

[http://www.jlab.org/Hall-D/detector/fdc/general/BLUECRAB_LAYOUT_08_04_2010.pdf floor plan]

    • Wire winding options: IUCF, JLab using UVA equipment, or using SSC winding machine?
  1. Updates on the redesigns
    • finalizing the PCB design

[http://www.jlab.org/Hall-D/detector/fdc/electronics/Readout_left.pdf Readout_left] [http://www.jlab.org/Hall-D/detector/fdc/electronics/HVright.pdf HV_right] [http://www.jlab.org/Hall-D/detector/fdc/electronics/HVleft.pdf HV_left] [http://www.jlab.org/Hall-D/detector/fdc/electronics/Readout_right.pdf Readout_right]

    • Cathode redesign
    • results from the tests of the new frame prototype
  1. Full scale prototype
    • three-layer HV tests (Beni)
    • preparation for cosmics tests