Participants: Bill, Mark, Casey, Simon, Eugene, Glenn, Fernando, Beni, Lubomir, and Gerard on the phone
+
Participants: Bill, Eugene, Mark, Brian, Casey, Beni, Simon, Lubomir, Gerard (on the phone), and  Glenn and Fernando (at the end)0
  
 
== Production ==         
 
== Production ==         
  
- Bill has given updated drawings with our requirements for the off-site space to Ron Bartek. Ron will work on the infrastructure of that building.
+
- Bill inform us that Ron Bartek has finished the design and the specifications for the infrastructure of the off-site space were given to the procurement. The information is that a DOE approval might be required. Eugene will contact Teresa Danforth to speed up the process.
  
- Bill has reviewed the production planing document linked above. There were several questions regarding the testing of the FDC layers and packages with cosmics. What we want to do will depend on the available time. For now we assume one day-night for testing per layer. We will come to this again after creating the production flowchart (Bill will take care about the latter). Fernando explained us the procedures related the the PCB inspections/tests. We need to set-up a place for testing, preferably in 117, and have one person trained  for that. Bill mentioned that (from mechanical point of view) the most important is the quality of the PCB edges.
+
- Bill will take care about creating the production flowchart based on the above document.
  
 +
- We discussed a plan to build a one-layer prototype based on the new designs of the frames, PCBs, and cathodes, and also using the UVA equipment for wire stringing. We will use the first article PCBs and cathodes to make the prototype. Brian will help with the transportation of the wire equipment from UVA; Lubomir will contact Nilanga in this respect, as well. The idea is to set up first the wire stringing at room 117.
 +
 +
<!--
 
== Electronics ==
 
== Electronics ==
  

Revision as of 16:19, 27 May 2010

May 27, 2010 FDC meeting

Tentative Agenda

  1. Production
  2. Electronics
  3. Cathode redesign Bill's changes proposed on the last meeting (Bill, Roger)
  4. Full-scale prototype test results
  5. Other



Minutes

Participants: Bill, Eugene, Mark, Brian, Casey, Beni, Simon, Lubomir, Gerard (on the phone), and Glenn and Fernando (at the end)0

Production

- Bill inform us that Ron Bartek has finished the design and the specifications for the infrastructure of the off-site space were given to the procurement. The information is that a DOE approval might be required. Eugene will contact Teresa Danforth to speed up the process.

- Bill will take care about creating the production flowchart based on the above document.

- We discussed a plan to build a one-layer prototype based on the new designs of the frames, PCBs, and cathodes, and also using the UVA equipment for wire stringing. We will use the first article PCBs and cathodes to make the prototype. Brian will help with the transportation of the wire equipment from UVA; Lubomir will contact Nilanga in this respect, as well. The idea is to set up first the wire stringing at room 117.