Difference between revisions of "Minutes-5-29-2014"

From GlueXWiki
Jump to: navigation, search
Line 20: Line 20:
 
== Gas system ==
 
== Gas system ==
  
- Both CDC and FDC are now connected to the gas system. Some minor issues (like tube/cable swapping, gas settings) were resolved. FDC bubbles at 50 sccpm per package but now we are flushing it with 100 sccpm (nominal is 200 sccpm per package). CDC is being flushed with 1l/m (nominal 3l/m).
+
- Both CDC and FDC are now connected to the gas system. Some minor issues (like tube/cable swapping, gas settings) were resolved. FDC bubbles at 50 sccpm per package but now we are flushing it with 100 sccpm (nominal is 200 sccpm per package). CDC is being flushed with 1l/m (nominal 3l/m). From the gas GUI for experts (attached) we see the pressures in the individual cells within a FDC package are very similar. Bill is surprised and requested testing at different scanning times. When all the solenoid valves are closed the pressure sensor reads high pressure that increases; could be explained by heat flow. 
  
- We were having problems with the gas control panel for the FDC: the display would disappear and then it requires turning off/on the power several times to reappear and some of the settings may be wrong. We are also not sure the
+
- We were having problems with the gas control panel for the FDC: the display would disappear and then it requires turning off/on the power several times to reappear and some of the settings may be wrong. We are also not sure if it is only display problem or also the gas flow is disrupted. Maybe related to that: we need to fill the mixing tank with a flow that is a factor of 2 bigger than what is expected from the FDC usage. We need a spare control panel (Eugene requested a price estimate).
  
- It turned the FDC part, including the mixing tank, were flushed over the weekend with 60/40 Ar/CO2 gas mixture, instead of 40/60. On Tuesday/Wednesday the detector was also flushed with the wrong gas mixture and as a result there were HV trips at that time.  
+
- It turned out the FDC part, including the mixing tank, were flushed over the weekend with 60/40 Ar/CO2 gas mixture, instead of 40/60. On Tuesday/Wednesday the detector was also flushed with the wrong gas mixture and as a result there were HV trips at that time.  
 
+
<!--
+
 
   
 
   
 
== CDC status ==   
 
== CDC status ==   
  
- Beginning of the week Beni and Mike started flushing the CDC with 40/60 pre-mix bottle at 1 l/min. HV of one sector at 2150V. Mike sees the first signals, though with low amplitudes, assumes due to oxygen contamination.  
+
- Mike: still can't have all the HV channels working: the problems is in the CAEN modules. Will use one 1535P module instead of 1550P but that is not enough. Mike will do another CDC leakage test. The temperatures at the pre-amps are oscillating by 1-1.5 deg; still using the same cooling.    
  
- Mike: mainly problems with the HV modules. With the help of Nick trying to replace some bad modules to have full system working. After replacing a module without turning off the power and then restarting the HV crate the hardware limits changed by up to few hundred vols!   
+
== Electronics ==
 +
 
 +
- Fernando: will discuss the HV issues with the CAEN people and request additional checks. Two HV modules are being repaired now, three were repaired before, all having problems with setting/holding HV. In addition we have many channels showing dark current of 0.5-1 uA without anything connected to the module. Eugene wanted to know haw many spare modules we will need. 
  
 
== Engineering ==
 
== Engineering ==
  
- Bill (not at the meeting) is looking for a camera to attach to the CMM to scan the cathode at JLab. Simple web camera doesn't work, it also has to have remote focusing.  
+
- We discussed once more if we want to scan the spare cathode with the JLab CMM machine; Eugene is reluctant since it requires (Bill) special stiff arm to hold the camera. Instead Eugene suggested to do measurements with a special ruler/magnifier only at the places where we suspect the original scan had problems.  
  
- Fluorinert level went down by ~2 cm in one month. Dave and Casey were trying the find the leakage with a sniffer without success. Casey will make a tube to sniff inside the magnet. We are going to weigh the quantity the is needed too refill the chiller and estimate the cost. Bill also proposed to put the chiller on a scale.
+
- The chiller was put on scale and will check the weight in a month to estimate the Fluorinert leakage. Casey got the parts to make the extension for the sniffer to look for the leakage.
 
+
== Electronics ==
+
 
+
- After Chris checked all the channels in the Beni's, Fernando concluded that only three of them have problems in the detector (that we knew already about) and further studies will be done with the fADC125 pulser when the firmware will available.  
+
  
 
== FDC alignment ==
 
== FDC alignment ==
  
- Lubomir: first iteration of the alignment of the third package using cosmics done. The corrections to the rotations and pitch values, and the offsets of the cathodes are shown in a table linked above. They correspond to about 0.5mm uncertainties when positioning the frame on the cathodes which is reasonable. As Eugene requested, Lubomir will estimate the errors of these corrections.
+
- Lubomir showed results about the FDC resolutions.
 
+
-->
+

Revision as of 12:53, 30 May 2014

May 29, 2014 FDC+CDC meeting

Agenda

  1. Gas system gas panel
  2. DAQ (Beni)
  3. CDC status (Mike)
  4. Engineering (Bill)
  5. Electronics (Chris, Nick)
  6. FDC alignment [1] (Lubomir)
  7. Other

Instructions for Bluejeans meeting connection

FDC meeting ID: 290664653

Minutes

Participants: Curtis, Naomi (CMU), Eugene, Bill, Dave, Chris, Nick, Simon, Fernando, Mike, and Lubomir (JLab).

Gas system

- Both CDC and FDC are now connected to the gas system. Some minor issues (like tube/cable swapping, gas settings) were resolved. FDC bubbles at 50 sccpm per package but now we are flushing it with 100 sccpm (nominal is 200 sccpm per package). CDC is being flushed with 1l/m (nominal 3l/m). From the gas GUI for experts (attached) we see the pressures in the individual cells within a FDC package are very similar. Bill is surprised and requested testing at different scanning times. When all the solenoid valves are closed the pressure sensor reads high pressure that increases; could be explained by heat flow.

- We were having problems with the gas control panel for the FDC: the display would disappear and then it requires turning off/on the power several times to reappear and some of the settings may be wrong. We are also not sure if it is only display problem or also the gas flow is disrupted. Maybe related to that: we need to fill the mixing tank with a flow that is a factor of 2 bigger than what is expected from the FDC usage. We need a spare control panel (Eugene requested a price estimate).

- It turned out the FDC part, including the mixing tank, were flushed over the weekend with 60/40 Ar/CO2 gas mixture, instead of 40/60. On Tuesday/Wednesday the detector was also flushed with the wrong gas mixture and as a result there were HV trips at that time.

CDC status

- Mike: still can't have all the HV channels working: the problems is in the CAEN modules. Will use one 1535P module instead of 1550P but that is not enough. Mike will do another CDC leakage test. The temperatures at the pre-amps are oscillating by 1-1.5 deg; still using the same cooling.

Electronics

- Fernando: will discuss the HV issues with the CAEN people and request additional checks. Two HV modules are being repaired now, three were repaired before, all having problems with setting/holding HV. In addition we have many channels showing dark current of 0.5-1 uA without anything connected to the module. Eugene wanted to know haw many spare modules we will need.

Engineering

- We discussed once more if we want to scan the spare cathode with the JLab CMM machine; Eugene is reluctant since it requires (Bill) special stiff arm to hold the camera. Instead Eugene suggested to do measurements with a special ruler/magnifier only at the places where we suspect the original scan had problems.

- The chiller was put on scale and will check the weight in a month to estimate the Fluorinert leakage. Casey got the parts to make the extension for the sniffer to look for the leakage.

FDC alignment

- Lubomir showed results about the FDC resolutions.