Difference between revisions of "Minutes-6-30-2011"

From GlueXWiki
Jump to: navigation, search
Line 27: Line 27:
 
- Dave (see the Construction Tracking link above): cell#3: cathode type-2 needs three rigid-flexes (they were glued but Casey found they had solder bridges on the connectors), cathode type-1: the rigid-flexes to be glued. Since Monday we stopped working on the wire frame that was strung, due to possible tension problems discussed later. cell#4: first cathode tensioned, gluing foils for the second one. In addition techs are laminating wire frames, 6 ready so far. Beni asked if we  cover the wires while soldering; not yet but we have the cover ready and will try it for the next wire plane. So far we have seen one solder ball on the wires, and Casey removed it.
 
- Dave (see the Construction Tracking link above): cell#3: cathode type-2 needs three rigid-flexes (they were glued but Casey found they had solder bridges on the connectors), cathode type-1: the rigid-flexes to be glued. Since Monday we stopped working on the wire frame that was strung, due to possible tension problems discussed later. cell#4: first cathode tensioned, gluing foils for the second one. In addition techs are laminating wire frames, 6 ready so far. Beni asked if we  cover the wires while soldering; not yet but we have the cover ready and will try it for the next wire plane. So far we have seen one solder ball on the wires, and Casey removed it.
  
- Lubomir on second cell HV tests: the cell is assembled as a package, now with lexan sheet on the top. The gas is runinng since Tuesday evening and since Wednesday we are conditing the chamber. Today we are at 1800V/-500V with a current of 120-130nA for the whole chamber, which is at least 10 times smaller than the first cell. So, most likely the HV problems we had with the first cell are due to the ultrasonic cleaning in water (which doesn't surprise anybody).     
+
- Lubomir on second cell HV tests: the cell is assembled as a package, now with lexan sheet on the top. The gas is runinng since Tuesday evening and since Wednesday we are conditioning the chamber. Today we are at 1800V/-500V with a current of 120-130nA for the whole chamber, which is at least 10 times smaller than the first cell. So, most likely the HV problems we had with the first cell are due to the ultrasonic cleaning in water (nobody was surprised).     
 
    
 
    
 
- Thanks to Bert Manzlak and RadCon people there's a signficant progress with the source usage at Blue Crab. Keth Welch proposed using 25 micro-Curie 55Fe source which is bellow all regulation limits, but according to JLab rules they will most likely require creating RCA at Blue Crab and some additional restriction. Yesterday Bert and  
 
- Thanks to Bert Manzlak and RadCon people there's a signficant progress with the source usage at Blue Crab. Keth Welch proposed using 25 micro-Curie 55Fe source which is bellow all regulation limits, but according to JLab rules they will most likely require creating RCA at Blue Crab and some additional restriction. Yesterday Bert and  

Revision as of 17:19, 30 June 2011

June 30, 2011 FDC meeting

Agenda

  1. Production (Dave)
  2. Engineering (Bill)
    • Package flatness measurements
    • FDC cabling
    • Other: gusset rings, lifting frame
  3. Electronics update (Fernando, Chris)
  4. Chamber testing at EEL126 (Beni, Lubomir)
  5. Other


Minutes

Participants: Eugene, Bill, Dave, Chris, Mark, Roger, Simon, Beni, and Lubomir.

Production

- Dave (see the Construction Tracking link above): cell#3: cathode type-2 needs three rigid-flexes (they were glued but Casey found they had solder bridges on the connectors), cathode type-1: the rigid-flexes to be glued. Since Monday we stopped working on the wire frame that was strung, due to possible tension problems discussed later. cell#4: first cathode tensioned, gluing foils for the second one. In addition techs are laminating wire frames, 6 ready so far. Beni asked if we cover the wires while soldering; not yet but we have the cover ready and will try it for the next wire plane. So far we have seen one solder ball on the wires, and Casey removed it.

- Lubomir on second cell HV tests: the cell is assembled as a package, now with lexan sheet on the top. The gas is runinng since Tuesday evening and since Wednesday we are conditioning the chamber. Today we are at 1800V/-500V with a current of 120-130nA for the whole chamber, which is at least 10 times smaller than the first cell. So, most likely the HV problems we had with the first cell are due to the ultrasonic cleaning in water (nobody was surprised).

- Thanks to Bert Manzlak and RadCon people there's a signficant progress with the source usage at Blue Crab. Keth Welch proposed using 25 micro-Curie 55Fe source which is bellow all regulation limits, but according to JLab rules they will most likely require creating RCA at Blue Crab and some additional restriction. Yesterday Bert and