Difference between revisions of "Minutes-7-14-2011"

From GlueXWiki
Jump to: navigation, search
 
(9 intermediate revisions by the same user not shown)
Line 17: Line 17:
 
# Other: [http://www.jlab.org/Hall-D/detector/fdc/tracking/FDC_NamingConvention.pdf naming convention]
 
# Other: [http://www.jlab.org/Hall-D/detector/fdc/tracking/FDC_NamingConvention.pdf naming convention]
  
<!--
 
  
 
= Minutes =
 
= Minutes =
  
Participants: Eugene, Bill, Dave, Chris, Beni, Simon, Caleb, and Lubomir.
+
Participants: Bill, Dave, Chris, Elton, Beni, Simon, Glenn, Caleb, and Lubomir.
  
 
== Production ==
 
== Production ==
  
- Dave: see  the construction tracking link above. For cell#3: gluing the rigid-flexes on the cathodes, some delay here was due problems with the connectors on three of the rigid-flexes and also we run out of tinned flexes and Casey had to tin the un-tinned. We continued with the wire frame#3, we postponed the production for a week since we were not sure about the problem with the frame deformation. The wires were taped and position measurements were done with the new code. Caleb reported that the number of field wires that can't be find increased from the last week. Techs are working on the cell#4 cathodes.
+
- Dave (see  the construction tracking): Cell#3 is almost ready, just second phase elements has to be put on the wire frame. The cathodes on cell#4 are ready except the flaps on the type-2 cathode. Now the techs are working on the cathodes for cell#5 using the two tensioning tools. We decided to postpone the wire frame production till we make a decision how to solve the HV problem, discussed later.  
  
- Lubomir on second cell tests: it was conditioned over the holidays
+
- Wire deadening: waiting for the chemicals needed. We will use the square lexan plate for tooling, but Bill will order another plate to be used for this procedure. Bill talking to Brian learned that the chemicals have to be neutralized at the end of the procedure and that was not always done before when experimenting on a testing wire frame. We will try the deadening first on several testing frames before using a production one. Dave with Al's help is finishing the micro-controller and also working on a way to bypass the 1M resistors on each wire channel.
by Anatoly (it took a week in total) and now it holds 2200V, but still
+
tripping every 2-3 hours. The trips might be due to the lexan sheet on the top.
+
Bill proposed to make it conductive for the future tests.
+
The current is very low, 140nA for the whole
+
chamber, especially compared to the first chamber that in similar conditions
+
had ~500nA on one sector and several uA on the rest.
+
 
+
- To find the origin of the current and trips, we checked separately
+
on another laminated wire frame: (1) the current through the HV boards and
+
found to be very small (so the Rohacell is not contributing to the current!)
+
(2) the current through the HV capacitors on the signal side:
+
this current turned out to be significant, between 10 nA and few hundred nA
+
at 2200V.  For 96 capacitors one would expect > 1 uA.
+
We will continue investigating the capacitors.
+
  
 
== Engineering ==
 
== Engineering ==
  
- Survey of the first package showed out of plane deviations up to 5.5mm in
+
- Bill ordered the strong-back for the packages. One option would be to attach it to the package after it is assembled, and the other is just to assemble the package on the top of the strong-back in which case we need several of them. We want to have flatness on the chambers better than 200 microns, but Bill says with the material budget we have it is hardly possible. Measurements on the gusset ring only show deviation from flat up to 150 microns. The biggest deviation correlates with some scratches made in the production and Bill wants to re-enforce that place with epoxied fiber.  
horizontal position and that effect goes with the gravity, and ~1mm in
+
vertical position. This explains the top/bottom asymmetry results.
+
  
- Bill explained the current design of the connections between the packages.
+
- While the stringing table is not used for now, Bill will modify the strong-back to correct for the flatness deviations. Additional holes needed for the frame ejection plate have to be drilled, as well.
We exchanged different ideas how to use this construction to correct for
+
the out-of-plane deviations of the packages.
+
 
+
- One of the gusset rings is ready and we can start re-assembling the second
+
cell. A survey of the strong-back for the wire frame showed sagging of ~2mm.
+
Bill says it is easy to correct it and it will do it after we are done with
+
the third wire frame. We discussed also what do we need to start the wire
+
deadening.
+
  
 
== Electronics ==
 
== Electronics ==
  
- Chris: 80 FDC type-1 cables were tested, found one bad. Another 130 FDC cables came, not tested yet.
+
- Lubomir and Anatoly did some tests to study the currents through the HV capacitors. At Blue Crab, one wire frame without wires was put in a gas volume (same 40/60 Ar/CO2) and HV was applied on the signal boards between the wire pads (connected with Cu tape) and the ground. The conditioning of this "wireless" chamber turned out to be very similar to the behavior of the second cell and maybe even worse. After almost a week we could reach only ~1.5kV while limiting the current below 1uA for the whole chamber. This indicates that the HV problems we had with cell#2 could be related to the capacitors on the signal boards.
- Eugene: all the ASICS will be ready by the end of the month, but making the pre-amp cards will take many months.
+
 
 +
- Fernando and Chris did similar tests with one signal board in 117. Initially the current was huge, few hundred uA at 1kV. Then Fernando suggested to cover the capacitors with humiseal and that helped. Initially the current was also high but on the next day it went down to ~13uA at 2kV for the whole board.
 +
 
 +
- Beni: these currents are much bigger than on the prototype and we should replace the HV capacitors with better ones and see if this will help. Elton: there were problems with the HV capacitors for the FCAL bases and they had to change them. We discussed how to proceed, certainly we need to know the origin of the currents. These measurements depend on the humidity, but the capacitors on the signal board are covered with humiseal. So, Chris will measure the current on each capacitor and depending on the results will replace those with high current with capacitors rated for higher voltage. We will do similar tests with the frame at Blue Crab: will cover it with humiseal and then, after conditioning, will identify the capacitors with highest current and eventually replace them.  
  
 
== Chamber testing ==
 
== Chamber testing ==
  
- As before, we can use one out of four HV sectors. After having understood
+
- Lubomir showed results (page 569 FDC logbook) for the strip resolution on cell#1 using fADC: it is below 200 microns and similar to the resolution obtained with the prototype.
the effects of the frame deformation, we are now studying the chamber
+
resolution. So far it's not as good as on prototype, especially on the top
+
strips. However, by swapping the cards at the detector it turned out that
+
the effect goes with the card. So, the problem could be in the
+
cards, cables, fADC, or the analysis code.
+
  
== Other ==
+
- Beni is testing now the cell#1 with external tracking and using discriminator cards with F1TDC and CAEN ADC for the cathodes. His first results about the strip resolution are similar to the above. 
  
- Eugene asked Dave how we are the production schedule. Dave: we are late by about a month but expect the be on track for the first package.
+
- To estimate the wire resolution on the prototype we used the angle reconstructed from the external chamber (even with poor coordinate resolution the base is big enough to have good angular resolution) and also used two wire frames with parallel wires. Simon will work on the code to estimate the resolution when the wires are not parallel to test the whole package.  
 +
 
 +
== Other ==
  
-->
+
- We looked again at the FDC naming convention (see link above) that we discussed already a year ago and was used for labeling the PCBs and foils. We agreed on it. Simon will implement it also in the off-line code, where appropriate.

Latest revision as of 12:58, 15 July 2011

July 14, 2011 FDC meeting

Agenda

  1. Production Construction Tracking (Dave)
    • Status
    • Wire deadening
  2. Engineering (Bill)
    • Flatness problem: package strongback, gusset rings
    • Stringing table modifications
  3. Electronics (Chris)
    • HV tests
    • Other
  4. Chamber testing at EEL126
    • First cell tests with fADC: cathode resolution(Lubomir)
    • Tests with external tracking (Beni)
  5. Other: naming convention


Minutes

Participants: Bill, Dave, Chris, Elton, Beni, Simon, Glenn, Caleb, and Lubomir.

Production

- Dave (see the construction tracking): Cell#3 is almost ready, just second phase elements has to be put on the wire frame. The cathodes on cell#4 are ready except the flaps on the type-2 cathode. Now the techs are working on the cathodes for cell#5 using the two tensioning tools. We decided to postpone the wire frame production till we make a decision how to solve the HV problem, discussed later.

- Wire deadening: waiting for the chemicals needed. We will use the square lexan plate for tooling, but Bill will order another plate to be used for this procedure. Bill talking to Brian learned that the chemicals have to be neutralized at the end of the procedure and that was not always done before when experimenting on a testing wire frame. We will try the deadening first on several testing frames before using a production one. Dave with Al's help is finishing the micro-controller and also working on a way to bypass the 1M resistors on each wire channel.

Engineering

- Bill ordered the strong-back for the packages. One option would be to attach it to the package after it is assembled, and the other is just to assemble the package on the top of the strong-back in which case we need several of them. We want to have flatness on the chambers better than 200 microns, but Bill says with the material budget we have it is hardly possible. Measurements on the gusset ring only show deviation from flat up to 150 microns. The biggest deviation correlates with some scratches made in the production and Bill wants to re-enforce that place with epoxied fiber.

- While the stringing table is not used for now, Bill will modify the strong-back to correct for the flatness deviations. Additional holes needed for the frame ejection plate have to be drilled, as well.

Electronics

- Lubomir and Anatoly did some tests to study the currents through the HV capacitors. At Blue Crab, one wire frame without wires was put in a gas volume (same 40/60 Ar/CO2) and HV was applied on the signal boards between the wire pads (connected with Cu tape) and the ground. The conditioning of this "wireless" chamber turned out to be very similar to the behavior of the second cell and maybe even worse. After almost a week we could reach only ~1.5kV while limiting the current below 1uA for the whole chamber. This indicates that the HV problems we had with cell#2 could be related to the capacitors on the signal boards.

- Fernando and Chris did similar tests with one signal board in 117. Initially the current was huge, few hundred uA at 1kV. Then Fernando suggested to cover the capacitors with humiseal and that helped. Initially the current was also high but on the next day it went down to ~13uA at 2kV for the whole board.

- Beni: these currents are much bigger than on the prototype and we should replace the HV capacitors with better ones and see if this will help. Elton: there were problems with the HV capacitors for the FCAL bases and they had to change them. We discussed how to proceed, certainly we need to know the origin of the currents. These measurements depend on the humidity, but the capacitors on the signal board are covered with humiseal. So, Chris will measure the current on each capacitor and depending on the results will replace those with high current with capacitors rated for higher voltage. We will do similar tests with the frame at Blue Crab: will cover it with humiseal and then, after conditioning, will identify the capacitors with highest current and eventually replace them.

Chamber testing

- Lubomir showed results (page 569 FDC logbook) for the strip resolution on cell#1 using fADC: it is below 200 microns and similar to the resolution obtained with the prototype.

- Beni is testing now the cell#1 with external tracking and using discriminator cards with F1TDC and CAEN ADC for the cathodes. His first results about the strip resolution are similar to the above.

- To estimate the wire resolution on the prototype we used the angle reconstructed from the external chamber (even with poor coordinate resolution the base is big enough to have good angular resolution) and also used two wire frames with parallel wires. Simon will work on the code to estimate the resolution when the wires are not parallel to test the whole package.

Other

- We looked again at the FDC naming convention (see link above) that we discussed already a year ago and was used for labeling the PCBs and foils. We agreed on it. Simon will implement it also in the off-line code, where appropriate.