= Minutes =
 +
Participants: Fernando, Bill, Roger, Mark, Bob, and Lubomir (fewer people
 +
because of the trigger meeting at CNU at the same time).
 +
 +
== Production ==
 +
 +
- According to Tim, the PR for the clean room is awaiting Claus Rode's signature.
 +
 +
- Long discussion about the production procedures. Bill included in the Fast Track also the wire frame production, the wire stringing, and the testing of
 +
the chamber layers. The file is linked above (as jpeg) and is open for
 +
discussions and improvements. Bill asked Mark to look at the file (with Fast
 +
Track from Tom) and give his comments. 8 technicians will be involved full day
 +
and will produce one layer for 6 days, but realistically we assume 8 days. For
 +
30 layers it will be 240 working days. In addition, two scientists will
 +
assemble the stack and do HV and cosmics tests. The exact tests are not yet
 +
defined, but the idea is to use all the time available for such tests, but not
 +
more than needed for the layer production. Fernando asked about the cleaning
 +
of the wire frames after soldering and we discussed different options for
 +
ultrasonic cleaning. Fernando wanted to have a flow chart of the production
 +
with dates, so that he knows when the different components are needed for the
 +
production. One of the main unknown is when realistically we can move to the
 +
off-site space and start organizing the production.  The plan is to have the
 +
wire frames by 8/24 (first article) and 9/20 (all 30). According to Fernando
 +
we will have the PCBs by 7/19 (first article) and by 8/19 (all). The PR for
 +
the cathode foils will be submitted next week and the timing of their
 +
production is not known yet, but Roger has contacted the company: they can do
 +
the first article by the middle of August (assuming the procurement doesn't
 +
take a lot of time). Using this information, Lubomir will start working on the
 +
flow chart with dates on it.
 +
 +
- Bill explained us his ideas about the wire stringing. He will use the strong-back that is at IUCF. Lubomir will take care of bringing the
 +
strong-back to JLab. The idea is to use tape pads to hold the wires at the
 +
right positions before gluing and soldering them. The wire positions will
 +
adjusted by hands (or with some tool) using the camera. We discussed once more
 +
different options for the tension measurements.
 +
 +
- the templates for the  rohacell arcs will be ready next Wednesday. Two students will start cutting the arcs, supervised by Mark. Bill said the most
 +
important is to have the I.D. cut correctly. The arcs will be stored in a box
 +
and then they will start gluing the rings.
 +
 +
== Electronics ==
 +
 +
- Fernando: CEM was awarded to produce the PCBs. After getting the first article (two of each) on 7/19, the PCBs will be tested by Fernando within
 +
two weeks before starting the mass production. In parallel, the first boards
 +
will be given to an outside company for stuffing, they will be tested again and
 +
then we will continue with the stuffing of all the boards.
 +
 +
- Lubomir looked with the differential probe at the output (with 18m cable) of the new anode and cathode cards. The dynamic range of the anode cards is
 +
about 2/3 of the range of the cathode cards; according to Fernando this is
 +
normal and comes from the difference in the gains. This explains the cutoff in
 +
the fADC spectra discussed before.
 +
 +
 +
== Cathode redesign ==
 +
 +
- Roger is ready with the design, except for a few cosmetic changes. He will send the Gerber files to the company by tomorrow and expects estimations
 +
from the company for 70 cathodes by the middle of the next week. At the same
 +
time he will start the PR paperwork, so that he can submit it as soon as he
 +
gets the quotation from the company.
 +
 +
== Full-scale prototype test results  ==
 +
 +
- Lubomir showed several Beni's plots, linked above. Based on high statistics cosmic data, the mean ADC, measuring the total charge from the wires, goes
 +
down with the drift time. Same was observed before for the maximum amplitude,
 +
using the fADC data. This can be explained by ~0.1% oxygen contamination. Beni
 +
also did measurements at different, by 20%, gas flow rates, but there's no
 +
visible change in the results.
 +
 +
- To measure the oxygen contamination we need a pump at the end of the oxygen sensor, as discussed last time. The problem is that the pressure there should
 +
not be less than 0.5 atm, according to the documentation of the sensor. Beni
 +
also confirmed this talking to the company. We will look what are the
 +
parameters of the pump that we have. We may need a relieve valve to keep the
 +
pressure there above half atm.
 +
 +
-->

Revision as of 15:49, 15 July 2010

July 15, 2010 FDC meeting

Tentative Agenda

  1. Production
  2. Electronics: update (Fernando)
  3. Engineering
    • Cathode foil: update (Roger)
    • Cathode frame prototyping
  4. Full-scale prototype tests
  5. Other