Difference between revisions of "Minutes-7-15-2010"

From GlueXWiki
Jump to: navigation, search
Line 18: Line 18:
  
 
<!--
 
<!--
 
 
= Minutes =
 
= Minutes =
 
Participants: Eugene, Fernando, Glenn, Roger, Mark, Casey, Beni, Simon, and Lubomir.
 
Participants: Eugene, Fernando, Glenn, Roger, Mark, Casey, Beni, Simon, and Lubomir.
Line 39: Line 38:
 
== Engineering ===
 
== Engineering ===
  
- Cathode foils: Roger showed us a plastic cylinder and a paper sample he received from the company to be used for transporting the foils. Mark said this paper should work (he had bad experience before with a sticky on one side paper). Fernando and Glenn suggested possible improvements: placing caps on the cylinder ends, using two cylinders with the foil in between. Roger will further communicate with the company to improve the packaging, while Mark and Casey will exercise packing using the company's paper. Roger is also checking the Gerber files and will send them soon to the company for quotation.  
+
- Cathode foils: Roger showed us a plastic cylinder and a paper sample he received from the company to be used for transporting the foils. Mark said this paper should work (he had bad experience before with a sticky on one side paper). Fernando and Glenn suggested possible improvements: placing caps on the cylinder ends, using two cylinders with the foil in between. There are also other questions that need to be iterated with the company, like how many foils will be rolled on one cylinder. Roger will further communicate with the company to improve the packaging, while Mark and Casey will exercise packing using the company's paper. Roger is also checking the Gerber files and will send them soon to the company for quotation.  
  
-  
+
- We have now two (one of each type) new design cathode frames machined in our machine shop. There was a problem with the vacuum fixture during the machining of one of the frames. According to Bill the procedure will change and this will not reoccur. Mark and Casey will prototype the new flapping design (to improve the grounding), using the foils that we have now. Roger will give them drawings to cut the flap according to the new design. Mark and Casey will also improve the procedure of gluing the foil to the transfer ring so that there's extra length to be used for the flaps.
  
 
== Full-scale prototype test results  ==
 
== Full-scale prototype test results  ==
  
- Lubomir showed several Beni's plots, linked above. Based on high statistics cosmic data, the mean ADC, measuring the total charge from the wires, goes
+
- Beni explained the procedure he used to calculate the wire resolution. The top two wire planes are read out, which wires are parallel. He plots the difference of the distances calculated from the drift times of the two layers as a function of the angle alpha (a drawing explaining this is attached above). He extracts the resolution for angles close to zero and gets about 200microns. The resolution is getting better if applying angle corrections. The dependence of the corrected difference
down with the drift time. Same was observed before for the maximum amplitude,
+
using the fADC data. This can be explained by ~0.1% oxygen contamination. Beni
+
also did measurements at different, by 20%, gas flow rates, but there's no
+
visible change in the results.
+
  
 
- To measure the oxygen contamination we need a pump at the end of the oxygen sensor, as discussed last time. The problem is that the pressure there should
 
- To measure the oxygen contamination we need a pump at the end of the oxygen sensor, as discussed last time. The problem is that the pressure there should

Revision as of 17:59, 15 July 2010

July 15, 2010 FDC meeting

Tentative Agenda

  1. Production
  2. Electronics: update (Fernando)
  3. Engineering
    • Cathode foil: update (Roger)
    • Cathode frame prototyping
  4. Full-scale prototype tests
  5. Other