Difference between revisions of "Minutes-7-22-2010"
From GlueXWiki
Line 27: | Line 27: | ||
== Production == | == Production == | ||
− | - No news about | + | - No news about Blue Crab. |
- Lubomir presented a Fatstrack version of the production with 5 people occupied, linked above. It will take ~12 working days to produce one layer (one wire and two cathode planes). This is to be compared to the previous version with 8 people producing one layer for ~6 working days. In case of 5 people, two techs are working on the two cathodes (one of them with a ground plane), one electrical tech is soldering the cathode connectors and the wires, two technicians are preparing the wire frame and string the wires. Eugene asked about other intermediate options: with 6,7 people available. Bill: the schedule will become realistic when we start the production (everybody agrees). Fernando: we must include additional, probably only visual inspection of the electrical part of the wire frames before starting the stringing. Berni: we should include the machining of the wire frames in the schedule even if it will be done outside. | - Lubomir presented a Fatstrack version of the production with 5 people occupied, linked above. It will take ~12 working days to produce one layer (one wire and two cathode planes). This is to be compared to the previous version with 8 people producing one layer for ~6 working days. In case of 5 people, two techs are working on the two cathodes (one of them with a ground plane), one electrical tech is soldering the cathode connectors and the wires, two technicians are preparing the wire frame and string the wires. Eugene asked about other intermediate options: with 6,7 people available. Bill: the schedule will become realistic when we start the production (everybody agrees). Fernando: we must include additional, probably only visual inspection of the electrical part of the wire frames before starting the stringing. Berni: we should include the machining of the wire frames in the schedule even if it will be done outside. | ||
− | |||
− | |||
− | - | + | - The strongbacks are being shipped from IUCF, will have them in a week or two. Bill wanted to have sketches or pictures of the position and tension measuring systems. Lubomir will contact UVA. |
− | + | ||
− | - | + | - The two Liping's students are busy with PRIMEX. We should start cutting the rohacells when we have people available. |
== Electronics == | == Electronics == |
Revision as of 22:43, 22 July 2010
July 22, 2010 FDC meeting
Tentative Agenda
- Announcements
- Production
- 727 B.C. status
- production planing: 5 techs production schedule
- Electronics: update (Fernando)
- Engineering
- Cathode foil: update (Roger)
- Wire stringing design (Bill)
- Cathode frame prototyping
- Full-scale prototype tests
- cosmic test results (Beni) FDC Log Book, pages 505
- oxygen contamination measurements Beni's scheme
- Other
Minutes
Participants: Eugene, Bill, Fernando, Glenn, Roger, Casey, Beni, Simon, and Lubomir.